Battery storage planning in Pembrokeshire

Pembrokeshire has decided 12 battery storage schemes and approved 92% of them, taking a median of 2.4 months to decide. Consented capacity: 752 MW. 2 applications still awaiting a decision.

92%
Approved
11 granted · 1 refused
2.4 mo
Median decision
UK 6 mo
752 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Pembrokeshire compares

Against the 137 UK authorities with 5+ battery storage decisions, Pembrokeshire sits in the 38th percentile for approval rate (level with the England average) and the 93rd percentile for speed.

Decisions by year

510Approved — 3 (2024)324Approved — 7 (2025)Refused — 1 (2025)825Approved — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (14)

SchemeMWStatusDecided
Castle Terrace, Pill Road - Battery Energy Storage
AMP Clean Energy · 25/0352/PA · 6.2 mo to decide
0.2Awaiting Construction2026-02-03
Fishguard Leisure Centre Car Park - Micro Energy Storage
AMP Clean Energy · 25/0351/PA · 4.2 mo to decide
0.2Application Refused2025-12-02
Meyrick Street - Micro Energy Storage System
AMP Clean Energy · 25/0348/PA · 2.1 mo to decide
0.2Awaiting Construction2025-09-30
Castle Quarry - Micro Energy Storage
AMP Clean Energy · 25/0355/PA · 1.8 mo to decide
0.2Awaiting Construction2025-09-22
Station Road, Brunel Quay - Micro Energy Storage
AMP Clean Energy · 25/0354/PA · 1.7 mo to decide
0.2Awaiting Construction2025-09-19
Bridge Innovation Centre, Pembrokeshire Science - Micro Energy Storage
AMP Clean Energy · 25/0347/PA · 1.7 mo to decide
0.2Awaiting Construction2025-09-18
Withybush Road, Withybush Industrial Estate - Micro Energy Storage System
AMP Clean Energy · 25/0349/PA · 1.7 mo to decide
0.2Awaiting Construction2025-09-18
St Daniels Hill - Micro Energy Storage Project
AMP Clean Energy · 25/0501/PA
0.2Application Submitted2025-09-05
Steynton Road And Sheffield Drive - Micro Energy Battery Storage
AMP Clean Energy · 25/0350/PA
0.2Application Submitted2025-07-28
Pembroke Power Station, Pwllcrochan - Battery Storage
RWE Generation UK Plc · 24/0600/PA · 4.5 mo to decide
350Awaiting Construction2025-01-31
Goldborough Road, Hundleton - Battery Energy Storage
Pembroke Green Limited (Enso Energy and Cero Generation) · 24/0133/PA · 7.9 mo to decide
350Awaiting Construction2025-01-06
The Greenlink Converter Station - Lambeeth Battery Energy Storage
Sirius EcoDev Limited · 23/0857/PA · 9.1 mo to decide
49.9Awaiting Construction2024-10-16
Honeyborough Industrial Estate - Micro Energy Storage Facility
Aggregated Micro Power Plc · 24/0388/PA · 1.8 mo to decide
0.2Awaiting Construction2024-09-18
Consort Equipment Products - Micro Energy Storage
Aggregated Micro Power Holdings Plc · 23/0990/PA · 2.7 mo to decide
0.2Awaiting Construction2024-05-24

Does Pembrokeshire approve battery storage schemes?

Yes — of the 12 battery storage schemes Pembrokeshire has decided, 92% were approved (11 granted, 1 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in Pembrokeshire?

The median time from application to decision is 2.4 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Pembrokeshire consented?

752 MW has been consented across 11 approved schemes. A further 2 applications awaits a decision.

Other technologies in Pembrokeshire

Solar in PembrokeshireOnshore wind in Pembrokeshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.