Renewable planning › Battery storage › Buckinghamshire
Battery storage planning in Buckinghamshire
Buckinghamshire has decided 11 battery storage schemes and approved 82% of them, taking a median of 9 months to decide. Consented capacity: 643 MW. 7 applications still awaiting a decision.
How Buckinghamshire compares
Against the 137 UK authorities with 5+ battery storage decisions, Buckinghamshire sits in the 14th percentile for approval rate (10 points below the England average) and the 19th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (21)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Stablebridge Road, Aston Clinton - Battery Storage AMP Clean Energy · PL/25/3479/FA · 4 mo to decide | 0.2 | Awaiting Construction | 2026-02-13 |
Mop End Farm, Mop End Lane - Battery Energy Storage Sandbrook Capital Bes Limited · PL/25/2447/FA | 500 | Application Submitted | 2025-08-15 |
Pinstone Farm, Oxford Road - Battery Energy Storage System Voltwise Power Holdings Limited · PL/25/2201/FA | 60 | Application Submitted | 2025-07-31 |
East Claydon Substation, East Claydon Road - Energy Storage Statkraft UK Limited · 25/01297/APP | 500 | Application Submitted | 2025-04-28 |
Hogshaw Road, Granborough - Battery Energy Storage System Root Power (South) Limited · 24/03262/APP | 99 | Application Withdrawn | 2025-03-17 |
East Claydon Battery Energy Storage Statera Energy · 23/03875/APP · 12.2 mo to decide | 500 | Awaiting Construction | 2024-12-20 |
Derehams Farm, Derehams Lane - Battery Storage Newton Energi Limited · 23/07053/FUL | 126 | Application Submitted | 2023-11-15 |
Derehams Farm, Derehams Lane - Battery Storage Eku Energy / Statkraft · 22/08045/FUL · 7.5 mo to decide | 40 | Operational | 2023-06-29 |
University Of Buckingham Campus, Energy Storage System AMP Energy Services Limited · 23/00894/APP | 0.2 | Application Withdrawn | 2023-05-22 |
Derehams Farm, Derehams Lane - Battery Storage Newton Energi Limited · 22/07255/FUL | 50 | Revised | 2023-05-05 |
Slough Road - Battery Storage Pivot Power · PL/21/3644/FA | 57 | Application Withdrawn | 2023-01-05 |
Whirlbush Farm, Kingsey - Solar Farm & Battery Storage Stark Energy · 21/02821/APP · 7.6 mo to decide | — | Awaiting Construction | 2022-03-03 |
Coldmoorholme Lane Battery Storage Envirotech Energy Solutions · 20/08321/FUL · 9 mo to decide | 7.2 | Application Refused | 2021-09-15 |
Stony Energy Storage Facility Gore Street Energy Storage Fund · 17/02259/APP · 49.7 mo to decide | 79.9 | Operational | 2021-09-03 |
Fox Covert Solar Farm Low Carbon · 20/02582/APP · 9.9 mo to decide | — | Operational | 2021-06-01 |
Gerrards Cross Sewage Treatment Works Peak Gen Power · PL/20/4234/FA | 20 | Application Submitted | 2020-12-23 |
Loudwater Battery Storage Site Capbal · 18/07600/FUL · 6.6 mo to decide | 40 | Revised | 2019-05-24 |
Church Farm Lightsource BP · 17/04036/APP · 16.8 mo to decide | — | Planning Permission Expired | 2019-03-14 |
Lye Green Energy Storage Harmony Energy Storage · PL/18/2421/FA | 25 | Appeal Refused | 2018-06-21 |
Litchlake Farm Hall Farm Energy · 17/02081/APP | 10 | Planning Permission Expired | 2017-05-31 |
Bumpers Lane Solar Farm Anesco · 14/A1926/NON | 13.3 | Operational | 2016-11-23 |
Does Buckinghamshire approve battery storage schemes?
Yes — of the 11 battery storage schemes Buckinghamshire has decided, 82% were approved (9 granted, 2 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in Buckinghamshire?
The median time from application to decision is 9 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Buckinghamshire consented?
643 MW has been consented across 9 approved schemes, with 32 MW refused. A further 7 applications awaits a decision.
Other technologies in Buckinghamshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.