Battery storage planning in Sheffield

Sheffield has decided 7 battery storage schemes and approved 100% of them, taking a median of 5.9 months to decide. Consented capacity: 50 MW. 2 applications still awaiting a decision.

100%
Approved
7 granted · 0 refused
5.9 mo
Median decision
UK 6 mo
50 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (7 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Sheffield compares

Against the 137 UK authorities with 5+ battery storage decisions, Sheffield sits in the 73rd percentile for approval rate (8 points above the England average) and the 49th percentile for speed.

Decisions by year

35Approved — 1 (2017)117Approved — 2 (2022)222Approved — 2 (2023)223Approved — 1 (2024)124
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (10)

SchemeMWStatusDecided
Yarra Industrial Estate, Loicher Lane - Battery Storage
Ecclesfield Power Limited · 22/03914/FUL · 19.1 mo to decide
20Awaiting Construction2024-05-30
Petre & Carlisle Street East & Petre Street - Battery Storage
Mercia Power Response · 23/00985/FUL · 2 mo to decide
Awaiting Construction2023-05-24
Hunsley Street - Battery Energy Storage
Mercia Power Response · 22/03606/FUL · 5 mo to decide
Awaiting Construction2023-02-28
Upwell Street - Battery Energy Storage
Newton Energi Limited · 22/01107/FUL · 6.8 mo to decide
Awaiting Construction2022-10-14
Darnall Road - Battery Energy Storage
Mercia Power Response Limited · 22/01021/FUL · 4.6 mo to decide
Awaiting Construction2022-08-02
Orgreave Place - Flexible Energy Facility
DBS 1 Limited · 26/00122/FUL
Application Submitted2021-06-16
Orgreave Place - Flexible Energy Facility
DBS 1 Limited · 21/01860/FUL
Revised2021-04-21
Petre Street
Renewable Energy Systems (RES) · 16/03302/FUL · 14.6 mo to decide
20Planning Permission Expired2017-11-24
Bochum Parkway
Tiger Energy · 17/00987/FL
Abandoned2017-09-14
Blackburn Meadows
E.ON UK
10Operational2011-08-19

Does Sheffield approve battery storage schemes?

Yes — of the 7 battery storage schemes Sheffield has decided, 100% were approved (7 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Sheffield?

The median time from application to decision is 5.9 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Sheffield consented?

50 MW has been consented across 7 approved schemes. A further 2 applications awaits a decision.

Other technologies in Sheffield

Solar in SheffieldOnshore wind in Sheffield

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.