Renewable planning › Battery storage › Angus
Battery storage planning in Angus
Angus has decided 18 battery storage schemes and approved 94% of them, taking a median of 6.2 months to decide. Consented capacity: 447 MW. 1 application still awaiting a decision.
How Angus compares
Against the 137 UK authorities with 5+ battery storage decisions, Angus sits in the 41st percentile for approval rate (2 points above the England average) and the 43rd percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (19)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Bindwells Battery Storage Facility OPDE UK Limted · 25/00249/FULM · 8.3 mo to decide | 49.9 | Awaiting Construction | 2026-02-04 |
Carseview Road - Battery Energy Storage System Unknown · 24/00765/FULM · 5.1 mo to decide | 49.9 | Awaiting Construction | 2025-06-11 |
Denfield - Battery Storage Facility Peter J Stirling Limited · 24/00589/FULL · 4 mo to decide | 7 | Awaiting Construction | 2025-02-14 |
Templeton Farm, Templeton - Battery Storage Fig Power · 24/00095/FULM · 8.2 mo to decide | 49.9 | Awaiting Construction | 2024-11-21 |
Denfield - Battery Storage Facility Peter J Stirling Limited · 23/00706/FULL | 7 | Revised | 2024-09-25 |
Bankhead, Arbirlot - Battery Energy Storage Ecocel Energy Storage Limited · 24/00178/FULM · 5.8 mo to decide | 49.9 | Awaiting Construction | 2024-09-19 |
Dunmill, Substation Dun - Battery Energy Storage Renewable Energy Systems Limited · 24/00038/FULM · 6.5 mo to decide | 49.9 | Awaiting Construction | 2024-08-14 |
Hillend Of Lownie - Forfar Solar farm Industria Resources Llp · 23/00393/FULM · 12.3 mo to decide | — | Application Refused | 2024-06-12 |
Balwyllo Farm, Dun - Energy Storage Facility Whirlwind Energy Storage Limited · 23/00754/FULM · 4.6 mo to decide | 49.99 | Awaiting Construction | 2024-03-13 |
Denfield Farm Seahills Properties Limited · 23/00285/FULL · 6.3 mo to decide | 20 | Awaiting Construction | 2024-01-05 |
Suttieside Farm, Suttieside Road - Solar Farm & Battery Storage Relay Suttieside Limited · 22/00870/FULM · 9.7 mo to decide | — | Awaiting Construction | 2023-12-13 |
Kinnell Farm, Kinnell - Solar Farm & Battery Energy Storage One Planet Developments Limited · 23/00484/FULL · 4.2 mo to decide | — | Awaiting Construction | 2023-11-20 |
Craignathro Farm - Solar Array Craignathro Farms Limited · 23/00077/FULL · 6.2 mo to decide | 6 | Awaiting Construction | 2023-08-17 |
Montreathmont Moor Forest - Solar Farm & Battery Storage Renewable Connections Developments Limited · 22/00460/FULM · 5.2 mo to decide | — | Awaiting Construction | 2022-12-16 |
Whitehills Energy Storage Facility Gigabox Developments Limited / Whirlwind Renewables · 21/00534/FULM · 5.3 mo to decide | 49.9 | Under Construction | 2021-12-15 |
Dragonhall Farm, Padanaram - Battery Storage Ecosse Solar Parks Limited · 21/00271/FULL | 10 | Under Construction | 2021-05-12 |
East Ballochy ScottishPower Renewables · 20/00019/FULM · 7.6 mo to decide | 10 | Awaiting Construction | 2020-09-15 |
Arbroath Battery Storage Coronation Power / Persimmon Homes · 18/00810/FULL · 9.9 mo to decide | 35 | Operational | 2019-08-20 |
Orchardbank Industrial Estate Capbal · 17/00848/FULL · 2.6 mo to decide | 10 | Planning Permission Expired | 2018-01-05 |
Does Angus approve battery storage schemes?
Yes — of the 18 battery storage schemes Angus has decided, 94% were approved (17 granted, 1 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in Angus?
The median time from application to decision is 6.2 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Angus consented?
447 MW has been consented across 17 approved schemes. A further 1 application awaits a decision.
Other technologies in Angus
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.