Battery storage planning in Westmorland and Furness

Westmorland and Furness has decided 7 battery storage schemes and approved 71% of them, taking a median of 8.8 months to decide. Consented capacity: 255 MW. 2 applications still awaiting a decision.

71%
Approved
5 granted · 2 refused
8.8 mo
Median decision
UK 6 mo
255 MW
Consented
50 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (7 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Westmorland and Furness compares

Against the 137 UK authorities with 5+ battery storage decisions, Westmorland and Furness sits in the 5th percentile for approval rate (21 points below the England average) and the 22nd percentile for speed.

Decisions by year

35Approved — 1 (2018)Refused — 1 (2018)218Approved — 2 (2023)223Approved — 1 (2025)125Refused — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (9)

SchemeMWStatusDecided
Trainriggs Shap - Solar Farm & Battery Storage
Abei Energy Limited · 2024/2358/FPA · 13.8 mo to decide
Application Refused2026-02-06
Roosecote Power Station, Rampside Road - Battery Energy Storage System
Centrica Plc · B03/2025/0281
50Application Submitted2025-08-27
Roxane UK, Armathwaite - Solar Array & Battery Storage
Roxane UK Limited · 2025/1585/FPA
1Application Submitted2025-08-19
Eskrigg End Road, Old Hutton - Battery Energy Storage System
Harmony MS Limited · 2024/2413/FPA · 9.2 mo to decide
200Awaiting Construction2025-07-10
Silver Howe, Flusco - Solar Array, Wind Turbines Battery Storage
Leisure Resorts · 22/0676 · 8.5 mo to decide
Awaiting Construction2023-05-19
Omega Proteins - Solar Farm & Battery Storage
Leo Group Limited · 21/0752 · 21.1 mo to decide
Awaiting Construction2023-05-19
Land at Calthwaite
Balance Power · 17/0925 · 2.4 mo to decide
6Planning Permission Expired2018-01-08
Greenmoor Bank
Greenmore Bank Storage · SL/2017/0425 · 7.9 mo to decide
50Application Refused2018-01-05
Roosecote
Centrica
49Operational

Does Westmorland and Furness approve battery storage schemes?

Yes — of the 7 battery storage schemes Westmorland and Furness has decided, 71% were approved (5 granted, 2 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Westmorland and Furness?

The median time from application to decision is 8.8 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Westmorland and Furness consented?

255 MW has been consented across 5 approved schemes, with 50 MW refused. A further 2 applications awaits a decision.

Other technologies in Westmorland and Furness

Solar in Westmorland and FurnessOnshore wind in Westmorland and Furness

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.