Scottish Government (S36) has decided 108 battery storage schemes and approved 94% of them, taking a median of 17.3 months to decide. Consented capacity: 17,631 MW. 105 applications still awaiting a decision.
How Scottish Government (S36) compares
Against the 137 UK authorities with 5+ battery storage decisions, Scottish Government (S36) sits in the 41st percentile for approval rate (2 points above the England average) and the 2nd percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (216)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Dunside Wind Farm EDF Energy · ECU00003436 · 33.2 mo to decide | 20 | Awaiting Construction | 2026-03-24 |
Ceislein Wind Farm RWE Renewables UK Limited · ECU00005174 | 65 | Application Submitted | 2026-03-13 |
Watchman Energy Park Renewco Power · ECU00006030 | 50 | Application Submitted | 2026-03-12 |
Inveroykel Wind Farm - Battery RWE Renewables UK Swindon Limited · ECU00005210 | — | Application Submitted | 2026-02-06 |
Creachan Wind Farm & BESS RWE · ECU00005211 | — | Application Submitted | 2026-02-05 |
Hare Hill Wind Farm Repowering SSE Renewables · ECU00004967 | — | Application Submitted | 2026-01-26 |
Clashindarroch Wind Farm Extension Infinergy · ECU00004695 · 35.2 mo to decide | 50 | Awaiting Construction | 2025-12-18 |
Earlsburn Avenue - Earlsburn Wind Farm Extension Naturalis Energy / REG Wind Power / Falck Renewables · ECU00004510 · 35.8 mo to decide | 18 | Awaiting Construction | 2025-12-16 |
Sclenteuch Wind Farm RES Limited · ECU00003318 · 41.2 mo to decide | 45 | Awaiting Construction | 2025-12-16 |
Gibson Farm, Blackhillock - Battery Energy Storage System Noriker Power Limited · ECU00005237 · 14.2 mo to decide | 349 | Awaiting Construction | 2025-12-03 |
Golticlay Wind Farm, Bulreanrob - Battery Energy Storage RWE Renewables UK Swindon Limited · ECU00006095 | — | Application Submitted | 2025-12-03 |
Mid Hill Wind Farm Invenergy Services UK · ECU00005192 | 53.2 | Application Submitted | 2025-11-27 |
Carrick Windfarm ScottishPower Renewables · ECU00003392 · 47 mo to decide | 20 | Application Refused | 2025-11-05 |
Craiginmoddie Wind Farm Energiekontor (UK) Limited · �ECU00002196 · 57.5 mo to decide | — | Awaiting Construction | 2025-11-05 |
Knockcronal Wind Farm Statkraft UK Limited · ECU00002181 · 47.6 mo to decide | — | Awaiting Construction | 2025-11-05 |
Salamander Offshore Wind Farm - Battery Storage and Onshore Connection Orsted / Simply Blue Group · ECU00005201 · 14.4 mo to decide | 180 | Awaiting Construction | 2025-10-28 |
Beinneun II Windfarm Beinneun 2 Ltd · ECU00004972 | 160 | Application Submitted | 2025-10-22 |
Hallyburton - Battery Storage Balance Power Projects Limited · ECU00004931 · 9.9 mo to decide | 100 | Awaiting Construction | 2025-10-02 |
East Rogerton Cottage, Markethill Road - Battery Storage Facility Apatura - GPC 680 Limited · ECU00006245 | 55 | Application Submitted | 2025-09-30 |
Titan Battery Storage Green Switch Capital Limited · ECU00005199 | 500 | Application Submitted | 2025-09-11 |
Kyllachy Wind Farm - BESS Wind Estate (UK) Limited · ECU00005153 | 22 | Application Submitted | 2025-09-05 |
Downiebrae Road, Rutherglen - Battery Energy Storage System Battery Box Limited · ECU00005091 · 7.7 mo to decide | 150 | Awaiting Construction | 2025-09-03 |
Sandy Knowe Wind Farm Extension Executive Resource Group · ECU00003274 · 36.3 mo to decide | 28.4 | Awaiting Construction | 2025-08-26 |
Netherton, Langside Road - Battery Energy Storage System Field Energy · ECU00006137 | 400 | Application Submitted | 2025-08-21 |
Redshaw Battery Energy Storage BayWa r.e. UK Limited · ECU00005122 · 5.4 mo to decide | 500 | Awaiting Construction | 2025-08-20 |
Stracathro - Battery Energy Storage System Opdenergy UK 8 Limited · ECU00004807 · 7.1 mo to decide | 249 | Awaiting Construction | 2025-08-13 |
Neilston Greener Grid Park - Phase 2 Statkraft UK LTD · ECU00004988 · 8.1 mo to decide | 750 | Awaiting Construction | 2025-08-13 |
Millennium East Renantis UK Limited · ECU00005013 | — | Application Submitted | 2025-08-13 |
Lagrae Battery Energy Storage System Buccleuch Estates Limited · ECU00004991 | 400 | Application Submitted | 2025-08-11 |
Meall Dearg Wind Farm - Wind Farm Energiekontor (UK) Limited · ECU00006049 | — | Application Submitted | 2025-08-11 |
Dorenell Extension Wind Farm Galileo · ECU00004862 | 20 | Application Submitted | 2025-08-08 |
Blackhills Wind Farm Koehler Renewable Energy · ECU00005136 | 20 | Application Submitted | 2025-08-07 |
Ballach Wind Farm Energiekontor (UK) Limited · ECU00005219 | 5 | Application Submitted | 2025-08-06 |
Kintore - Battery Energy Storage Mespil Solar Energy · ECU00005245 | 40 | Application Submitted | 2025-07-29 |
North Lanrigg Energy Storage North Lanrigg Battery Storage Limited · ECU00005166 · 12.3 mo to decide | 200 | Awaiting Construction | 2025-07-24 |
Roaring Hill, Whinnyknowe - Battery Energy Storage System ELM Power Limited · ECU00005104 | 60 | Application Submitted | 2025-07-23 |
Cockenzie Battery Storage System - Site A Gresham House · ECU00004926 · 22.8 mo to decide | 240 | Awaiting Construction | 2025-07-23 |
Cockenzie Battery Storage System - Site B Gresham House · ECU00006022 · 8.3 mo to decide | 102 | Awaiting Construction | 2025-07-23 |
Braxbess Battery Storage Braxbess Limited · ECU00004993 · 19.9 mo to decide | 650 | Awaiting Construction | 2025-07-23 |
Fernishaw Solar Farm & Battery Energy Storage Facility Elgin Energy (EEB67) · ECU00004871 · 19.1 mo to decide | 25 | Awaiting Construction | 2025-07-23 |
Kincardine Battery Storage Gresham House Devco Pipeline Limited · ECU00004987 · 11.7 mo to decide | 342 | Awaiting Construction | 2025-07-22 |
Holmquarry Road - Battery Storage Big Battery (Holmquarry Road) Limited · ECU00004539 · 16.5 mo to decide | 60.4 | Awaiting Construction | 2025-07-22 |
Belston Battery Storage KX Alpha Ltd · ECU00005141 · 7.8 mo to decide | 150 | Awaiting Construction | 2025-07-22 |
Whitehall Battery Storage Apatura · ECU00004982 · 20.2 mo to decide | 560 | Awaiting Construction | 2025-07-22 |
Limekiln, Borlum House - Battery Energy Storage System Boralex · ECU00006154 | 70 | Application Submitted | 2025-07-15 |
Giants Burn Wind Farm -Batter Energy Storage Statkraft UK Limited · ECU00005007 | 23 | Application Submitted | 2025-07-15 |
Rothienorman, Middleton of Blackhills - BESS Blackford Renewables Limited · ECU00006121 | 500 | Application Submitted | 2025-07-14 |
Dolphingstone Farm - Battery Energy Storage System RNA Energy Limited · ECU00004969 · 19.7 mo to decide | 63 | Awaiting Construction | 2025-07-04 |
Greystone, Blackhills - Battery Energy Storage System Peterhead Flexpower · ECU00006204 | 500 | Application Submitted | 2025-07-04 |
Flushing, Longside - Battery Energy Storage System Harmony Energy Storage · ECU00006086 | 400 | Application Submitted | 2025-07-04 |
Stirches Renewable Energy Park - Solar Panels & Battery Energy Storage IB Vogt UK Limited · ECU00006015 | 30 | Application Submitted | 2025-07-03 |
Womblehill Farm, Kintore - Battery Energy Storage System RE Projects Development (REPD) / Field · ECU00005233 | 200 | Application Submitted | 2025-06-27 |
Lower Bodachra - Energy Storage System Novus Renewables Services Limited · ECU00004848 · 9.4 mo to decide | 45 | Awaiting Construction | 2025-06-24 |
Inchbean Farm, Treeswoodhead Road - Battery Energy Storage System RNA Energy Limited · ECU00004968 · 19.3 mo to decide | 60 | Awaiting Construction | 2025-06-19 |
Red Moss - Battery Storage Green Switch Capital Limited · ECU00005043 · 5.1 mo to decide | 342 | Awaiting Construction | 2025-06-19 |
Coille Linne Wind Farm - Battery Energy Storage Energiekontor (UK) Limited · ECU00005163 | 5 | Application Submitted | 2025-06-18 |
Bowshiel Farm - Battery Energy Storage Voltalia UK · ECU00005085 | 80 | Application Submitted | 2025-06-06 |
Springfield - Solar Farm & Battery Energy Storage Voltalia UK Limited · ECU00004815 | 80 | Application Submitted | 2025-06-06 |
Windburn Wind Farm Octopus Energy / Wind 2 Limited · ECU00004782 | 35 | Application Submitted | 2025-06-05 |
Persley BESS - Battery Storage Anesco · ECU00005113 · 13.6 mo to decide | 70.05 | Awaiting Construction | 2025-06-04 |
Achies - Battery Energy Storage System Sun4net Limited · ECU00006111 | 162 | Application Submitted | 2025-06-03 |
High Boydstone Farm - Battery Energy Storage Facility New Energy Partnership · ECU00005094 · 7.7 mo to decide | 100 | Awaiting Construction | 2025-06-02 |
Lairdmannoch Energy Park Wind2 / Octopus Energy · ECU00004900 | 20 | Application Submitted | 2025-05-27 |
Kilwinning Battery Storage Apatura · ECU00005128 · 12.4 mo to decide | 100 | Awaiting Construction | 2025-05-21 |
Back Fell Wind Farm E Power Limited · ECU00004830 | 40 | Application Submitted | 2025-05-19 |
Learielaw Farm, Learielaw - Battery Energy Storage Intelligent Land Investments Group · ECU00004983 · 17.9 mo to decide | 100 | Awaiting Construction | 2025-05-19 |
Abbotshaugh Battery Storage Island Green Power (IGP Solar 25 Limited) · ECU00005224 | 500 | Application Submitted | 2025-05-16 |
Cossans Solar Farm -ESS BLC Energy · ECU00005213 | 35 | Application Submitted | 2025-05-15 |
Salters Battery Energy Storage System Buccleuch Group · ECU00004962 · 8.7 mo to decide | 200 | Awaiting Construction | 2025-05-12 |
High Netherfauld House Farm 1, Tower Road - Battery Energy Storage System ESB (Harker) Limited · ECU00006063 | 502.5 | Application Submitted | 2025-05-12 |
Kinmuck Battery Energy Storage Kinmuck Energy Storage Limited / Island Green Power · ECU00004907 · 19.8 mo to decide | 105 | Awaiting Construction | 2025-05-08 |
Hagshaw Energy Cluster � Western Expansion 3R Energy Solutions Limited · ECU00004623 | 225 | Application Submitted | 2025-05-08 |
Kintore Battery Energy Storage Project Alcemi Storage Development Limited · ECU00004756 · 50.7 mo to decide | 300 | Awaiting Construction | 2025-05-07 |
Tomchrasky Estate Wind farm E Power Limited · ECU00004663 · 29.5 mo to decide | 50 | Awaiting Construction | 2025-05-06 |
Mossmorran Battery Storage Gresham House Devco Pipeline · ECU00004985 · 10.5 mo to decide | 300 | Awaiting Construction | 2025-05-06 |
Ladyfield Renewable Energy Park Ridge Clean Energy Limited · ECU00003291 · 15.4 mo to decide | 41.4 | Awaiting Construction | 2025-05-02 |
Lynemore Wind Farm Galileo Empower UK Limited · ECU00005105 | 50 | Application Submitted | 2025-05-01 |
South Kyle Wind Farm 2 Vattenfall · ECU00003429 | 50 | Application Submitted | 2025-05-01 |
Knockkippen Wind, Solar & Battery Farm Falck Renewables / REG Windpower · ECU00004523 · 34.2 mo to decide | 16 | Awaiting Construction | 2025-04-30 |
Carlisle Road - Battery Energy Storage System Zenobe Energy · ECU00004799 · 22.7 mo to decide | 200 | Awaiting Construction | 2025-04-28 |
Braston New Energy New Energy Partnership · ECU00004995 · 12.6 mo to decide | 500 | Awaiting Construction | 2025-04-23 |
Cnoc Buidhe Windfarm Belltown Power Limited · ECU00004767 | 108.6 | Application Submitted | 2025-04-10 |
Kilmarnock Battery Energy Storage System Intergen Limited · ECU00004941 · 18.3 mo to decide | 500 | Awaiting Construction | 2025-04-07 |
West Springfield Solar Farm - Solar Panels & BESS BLC Energy · ECU00006134 | 35 | Application Submitted | 2025-04-02 |
Riccarton Mains Road - Battery Energy Storage Miller Developments · ECU00005144 | 150 | Application Submitted | 2025-03-26 |
Ourack Vattenfall · ECU00001999 · 29.2 mo to decide | 50 | Awaiting Construction | 2025-03-25 |
Pond Industrial Park, Whitburn Road - Pond Battery Storage Banks Renewables · ECU00004765 · 10.3 mo to decide | 200 | Awaiting Construction | 2025-03-24 |
Gretna Green Battery Storage Gresham House Devco Pipeline · ECU00004986 · 10.5 mo to decide | 456 | Awaiting Construction | 2025-03-17 |
Balblair Wind Farm Wind Power North Two Limited · ECU00005055 | 30 | Application Submitted | 2025-03-14 |
Bishops Dal - Battery Energy Storage System Renewable Energy Systems RES Limited (Beaufort) · ECU00005049 | 150 | Application Submitted | 2025-03-05 |
Corr Chnoc Wind Farm Galileo Green Energy Scotland Limited · ECU00006023 | 25 | Application Submitted | 2025-03-04 |
Blair Hill Wind Farm RES Limited · ECU00004878 | — | Application Submitted | 2025-03-03 |
Clune Wind Farm - Battery Energy Storage Renewable Energy Systems · ECU00005038 | 100 | Application Submitted | 2025-03-03 |
Glenside Farm - Battery Storage Apatura · ECU00005047 · 12.5 mo to decide | 400 | Awaiting Construction | 2025-02-25 |
Balnespick Wind Farm Fred Olsen Renewables Limited · ECU00004904 | 10 | Application Submitted | 2025-02-20 |
Earraghail Renewable Energy Development ScottishPower Renewables · ECU00003421 · 35.8 mo to decide | 25 | Application Refused | 2025-02-14 |
Allt an Tuir Renewable Energy Park REG Windpower Limited / ESB Energy Limited · ECU00005008 | 12 | Application Submitted | 2025-02-06 |
Corriemoillie Substation Garve - Battery Energy Storage Isenau Energy Storage Five Limited · ECU00005155 | 200 | Application Submitted | 2025-02-06 |
Former Fife Power Station - Battery Energy Storage System Fife Power 1 Ltd · ECU00005188 | 100 | Application Submitted | 2025-02-06 |
Newarthill Energy Park Geocore Limited · ECU00004953 · 14.9 mo to decide | 300 | Awaiting Construction | 2025-02-04 |
Neilston - Battery Storage Apatura (GPC 1119 Ltd) · ECU00004868 · 13.5 mo to decide | 150 | Awaiting Construction | 2025-02-04 |
Highland Wind Farm - Battery Storage Highland Wind Farm Limited · ECU00005082 | 30 | Application Submitted | 2025-01-31 |
Mid Moile Wind Farm EnergieKontor UK Limited · ECU00003405 · 35.5 mo to decide | — | Awaiting Construction | 2025-01-30 |
Crosbie Wind Farm Galileo Green Energy Scotland Limited (GGE Scotland) · ECU00004981 | 50 | Application Submitted | 2025-01-28 |
Glentarken Wind Farm SSE Renewables Wind Farms UK Ltd · ECU00004700 | 50 | Application Submitted | 2025-01-21 |
Rogerhill Solar and Battery Energy Storage System Green Switch Capital Limited · P/25/0018 | 100 | Application Submitted | 2025-01-15 |
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storage Scottish Power Renewables · ECU00002198 · 44.8 mo to decide | 50 | Awaiting Construction | 2025-01-09 |
Strath Oykel Wind Farm Energiekontor (UK) Limited · ECU00003246 · 31.8 mo to decide | 5 | Awaiting Construction | 2025-01-08 |
West Torrisdale Wind Farm ESB Asset Development UK · ECU00002224 | 20 | Application Submitted | 2025-01-06 |
Saturland Farm, Salterland Road - Battery Energy Storage System Resources Unlimited LLP · ECU00004590 · 13.1 mo to decide | 60.8 | Awaiting Construction | 2024-12-19 |
Dunballoch Farm, Dunballoch - Battery Energy Storage Field Energy · ECU00005160 | 100 | Application Submitted | 2024-12-19 |
Spittal Mains, Spittal - Battery Energy Storage System Field Spittal Limited · ECU00005116 | 300 | Application Submitted | 2024-12-19 |
Eccles II Substation - Battery Energy Storage System Intergen · ECU00004804 · 19.5 mo to decide | 500 | Under Construction | 2024-12-16 |
Braidfield Road, Hardgate - Battery Storage Facility Intelligent Land Investments Group Plc · ECU00006053 | 100 | Application Submitted | 2024-12-13 |
Flemyland Battery Storage Flemyland Battery Storage Limited · ECU00004984 · 12.5 mo to decide | 100 | Awaiting Construction | 2024-12-06 |
Cruach Clenamacrie Wind Farm Voltalia · ECU00004841 | 20 | Application Submitted | 2024-12-05 |
Haughend Farm - Alyth Battery Energy Storage System EcoDev Group Limited · ECU00004631 · 23.6 mo to decide | 900 | Awaiting Construction | 2024-11-26 |
Knocknagael, Essich - Battery Energy Storage System Knocknagael Limited · ECU00005099 | 200 | Application Submitted | 2024-11-22 |
Loch Awe - Eredine Wind Farm RWE Renewables UK Limited · ECU00004517 | — | Application Submitted | 2024-11-20 |
Glenvernoch Wind Farm Energiekontor (UK) Limited · ECU00004892 | — | Application Submitted | 2024-11-12 |
Clachaig Glen RWE UK · ECU00002103 · 31.7 mo to decide | 30 | Awaiting Construction | 2024-11-05 |
Whitehill Energy Storage Intelligent Land Investments Group · ECU00004632 · 24.6 mo to decide | 200 | Awaiting Construction | 2024-10-28 |
Loch Fergus Farm - Energy Storage System Locogen · ECU00004855 · 15.7 mo to decide | 45 | Under Construction | 2024-10-22 |
Balnuith Farm, Tealing - Battery Storage Apatura · ECU00004887 · 11.3 mo to decide | 100 | Awaiting Construction | 2024-10-22 |
Nettly Burn Renewable Energy Park Grupotec Solar UK 4 Ltd · ECU00006007 | 15 | Application Submitted | 2024-10-22 |
M74 West Renewable Energy Park Renewco Power · ECU00005019 | 50 | Application Submitted | 2024-09-24 |
Hollandmey Renewable Energy Development Scottishpower Renewables · ECU00003353 · 33.9 mo to decide | 15 | Awaiting Construction | 2024-09-16 |
Auchentiber Road - Battery Energy Storage System Apatura GPC 700 Limited · ECU00004979 · 9.9 mo to decide | 700 | Awaiting Construction | 2024-09-11 |
Tweed Valley, Southern Uplands - Oliver Forest Wind Farm Statkraft UK Limited · ECU00004669 | 23 | Application Submitted | 2024-09-04 |
Smeaton Battery Energy Storage System Kona Energy · ECU00004783 · 17.3 mo to decide | 228 | Awaiting Construction | 2024-08-29 |
Kilgallioch - Battery energy storage Scottish Power Renewables · ECU00002197 · 42 mo to decide | 100 | Awaiting Construction | 2024-07-16 |
Creag Riabhach Wind Farm Extension & Battery Storage Creag Riabhach Wind Farm Limited · ECU00004487 · 25.9 mo to decide | 37.3 | Awaiting Construction | 2024-07-05 |
Philips Mains, Mey - Battery Energy Storage Simec Atlantis Energy Limited · ECU00004838 | 300 | Application Submitted | 2024-06-10 |
Middleton Road - Linwood Battery Energy Storage System Bluestone Energy Limited · ECU00004543 · 14.8 mo to decide | 69 | Abandoned | 2024-05-16 |
Stirling Battery and Solar Energy Park EcoDev Group Limited · ECU00005014 | 50 | Application Submitted | 2024-05-16 |
Brunt Hill Wind Farm & Battery Storage E Power Limited · ECU00004654 | 50 | Application Submitted | 2024-05-08 |
Acheilidh Wind Farm (Previously known as Lairg III) Energiekontor (UK) Limited · ECU00004528 | 5 | Application Submitted | 2024-05-07 |
Armadale Wind Farm Brookfield Renewable UK · ECU00003455 | 42 | Application Withdrawn | 2024-05-07 |
Rowan Wind Farm Energiekontor UK Limited · ECU00003230 · 26.7 mo to decide | 5 | Awaiting Construction | 2024-04-26 |
Pittlesheugh Farm Bess, Springwells Farmhouse - Battery Energy Storage The Energy Workshop · ECU00004872 | 340 | Application Submitted | 2024-04-19 |
Lees Hill Energy Park Fred Olsen Renewables Limited · ECU00004571 | 60 | Application Submitted | 2024-04-16 |
Shinness Wind Farm Shinness Wind Farm Limited · ECU00004597 | 105 | Application Submitted | 2024-04-15 |
Leithenwater Wind Energy Hub - Wind Farm Belltown Power Limited · ECU00004619 | 10 | Application Submitted | 2024-04-04 |
Bunloinn Wind Farm Energiekontor (UK) Limited · ECU00003304 · 24.1 mo to decide | 5 | Awaiting Construction | 2024-04-02 |
Kellas Wind Farm E Power Limited · ECU00005054 | 30 | Application Submitted | 2024-03-19 |
Aultmore Forest - Buckie - Windfarm Vattenfall · ECU00003365 | 50 | Application Submitted | 2024-02-28 |
Lethen Wind Farm Wind Turbines and Energy Storage Fred Olsen Renewables Ltd · ECU00002216 · 25.1 mo to decide | 10 | Application Refused | 2024-02-23 |
Shetland Battery Energy Storage System Zenobe Energy · ECU00004881 · 6.8 mo to decide | 70 | Awaiting Construction | 2024-02-21 |
Cairn Duhie Wind Farm Renewable Energy Systems (RES) · �ECU00003225 · 34.3 mo to decide | — | Awaiting Construction | 2024-02-02 |
Camsiscan Farm, Craigie - Battery Energy Storage System Noriker Power Limited · ECU00004658 · 14.3 mo to decide | 350 | Awaiting Construction | 2024-01-26 |
Coalburn II Energy Storage Facility - Battery Storage Facility Alcemi Storage Development Limited · ECU00004698 · 13.6 mo to decide | 1000 | Awaiting Construction | 2024-01-24 |
Faw Side Community Wind Farm Community Windpower · ECU00001833 · 55 mo to decide | — | Application Refused | 2023-12-22 |
Thorntonloch, Innerwick - Branxton Energy Storage Facility EastCoastGridServices Limited · ECU00004659 · 13 mo to decide | — | Awaiting Construction | 2023-12-19 |
Chleansaid Onshore Wind Farm ESB · ECU00002031 · 20.5 mo to decide | 20 | Awaiting Construction | 2023-12-15 |
Tealing Battery Energy Storage Farm Sirius EcoDev Limited · ECU00003354 · 25.9 mo to decide | 80 | Awaiting Construction | 2023-12-13 |
Devilla Energy Storage Facility Alcemi Storage Development Limited · ECU00003469 · 19.8 mo to decide | 500 | Under Construction | 2023-12-13 |
Penicuik, Moorfoot Hills - Torfichen Wind Farm RES Limited · ECU00004661 | 50 | Application Submitted | 2023-11-28 |
Culachy Wind Farm Fred Olsen Renewables Limited · ECU00003423 | 10 | Application Submitted | 2023-11-17 |
Newlands Hill Wind Energy Hub Belltown Power Limited · ECU00004603 | 136 | Application Submitted | 2023-11-14 |
Hill of Fare - Hill of Fare Wind Farm & Battery Storage RES Limited · ECU00004592 | 100 | Application Submitted | 2023-11-06 |
Longcroft Wind Farm Renewable Energy Systems · ECU00004774 | 50 | Application Submitted | 2023-10-31 |
Vale of Leven Wind Farm Coriolis Energy Limited · ECU00003468 | 20 | Application Submitted | 2023-10-17 |
Houston Solar PV Farm & Energy Storage Facility The Old Rectory · ECU00004825 | 25 | Application Submitted | 2023-10-04 |
Cloud Hill Wind Farm Blue Energy Company / BayWa r.e. UK Limited · ECU00003461 | 34 | Abandoned | 2023-10-03 |
Clauchrie Windfarm Battery Scottish Power Renewables · ECU00002001 · 44.4 mo to decide | 25 | Application Refused | 2023-08-31 |
Sanquhar 2 Community Wind Farm Community Windpower · ECU00001801 · 53.4 mo to decide | — | Under Construction | 2023-08-31 |
Shepherd's Rig Wind Farm Boralex/Infinergy · ECU00000735 · 56.1 mo to decide | 6 | Awaiting Construction | 2023-08-21 |
Watten Wind Farm EDF Energy Renewables · ECU00004509 | 20 | Application Submitted | 2023-08-14 |
Eccles Battery Energy Storage System Zenobe Energy Limited · ECU00004601 · 10.9 mo to decide | 400 | Under Construction | 2023-08-11 |
Benthead Farm - Solar Farm & Battery Storage Locogen Limited · ECU00004702 · 8 mo to decide | 31.1 | Awaiting Construction | 2023-08-11 |
Ditcher Law Wind Farm E Power Ltd · ECU00004890 | 30 | Application Submitted | 2023-08-08 |
Glen Ullinish II - Wind Farm Muirhall Energy Limited · ECU00004829 | 120 | Application Submitted | 2023-07-31 |
Rivox Wind Farm - Wind farm Belltown Power Limited · ECU00003293 | 90 | Application Submitted | 2023-07-10 |
Bodinglee Wind Farm Banks Group · ECU00004839 | 106 | Application Submitted | 2023-06-22 |
Ben Aketil Wind Farm - Repowered & Extended Falck Renewables Limited · ECU00004552 | 20 | Application Submitted | 2023-06-09 |
Coalburn Energy - Battery Storage Alcemi Storage Development Limited · ECU00003458 · 14 mo to decide | 500 | Under Construction | 2023-06-07 |
Knockodhar Wind Farm REG Knockodhar Limited · ECU00002153 | 20 | Application Submitted | 2023-05-26 |
Abhainn Dubh Wind Farm E Power Limited · ECU00004732 | 30 | Application Submitted | 2023-05-19 |
Frodo Solar and Battery Energy Development Green Energy International · ECU00003345 · 14 mo to decide | 50 | Awaiting Construction | 2023-05-16 |
Greenburn Wind Park REG Windpower Limited · ECU00002037 · 36.8 mo to decide | 10 | Awaiting Construction | 2023-04-21 |
Melvich Bay - Melvich Wind Energy Hub Belltown Power Limited · ECU00004515 | 42 | Application Submitted | 2023-03-29 |
Mains Of Keithick Farm, Keithick - Battery Storage & Solar Farm EcoDev Group Limited · ECU00004521 · 8 mo to decide | 16 | Awaiting Construction | 2023-03-21 |
Quantans Hill Wind Farm Vattenfall Wind Power Limited · ECU00003399 | 50 | Application Submitted | 2023-01-27 |
Scawd Law Wind Farm Fred Olsen Renewables · ECU00002111 | 12 | Application Submitted | 2022-12-22 |
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facility Elgin Energy Es Co Limited · ECU00003226 · 22.3 mo to decide | 20 | Awaiting Construction | 2022-12-22 |
Chesters - Millmoor Rig Wind Farm & Battery Energy Storage ESB Asset Development UK Ltd · ECU00003426 | 20 | Application Submitted | 2022-11-28 |
Kirkton Energy Farm Kirkton Wind Farm Limited · ECU00003244 | 20 | Application Submitted | 2022-11-09 |
Bloch Wind Farm & Battery Storage (Solway Bank Extension) Renewable Energy Systems (RES) · ECU00003463 | 45 | Application Submitted | 2022-11-02 |
Clash Gour EDF Energy Renewables/ Force 9 · ECU00000738 · 46.1 mo to decide | 50 | Awaiting Construction | 2022-10-21 |
Windyhill Battery Storage Facility Energy GridPower Ltd · ECU00003361 · 7.6 mo to decide | 200 | Awaiting Construction | 2022-06-16 |
Craig Watch - Wind Farm & Battery Storage Craig Watch Wind Farm Limited · ECU00002177 | 27.4 | Application Submitted | 2022-06-14 |
Wemyss Estate - Randolph Solar Farm & Battery Energy Storage Elgin Energy · ECU00002222 · 14.5 mo to decide | 25 | Awaiting Construction | 2022-05-24 |
Teviot Wind Farm Muirhall Energy Limited · ECU00003249 | 100 | Application Submitted | 2022-05-20 |
Limekiln Wind Farm (Extension) - Battery Infinergy / Boralex · ECU00002070 · 23.7 mo to decide | 5 | Operational | 2022-05-06 |
Grayside Wind Farm Grayside WF · ECU00003446 | 20 | Application Submitted | 2022-03-31 |
Blackhillock Electricity Substation - Battery Energy Storage System Zenobe Energy Limited · ECU00003404 · 2.2 mo to decide | 300 | Under Construction | 2022-02-28 |
Kilmarnock South Substation - Battery storage Zenobe Energy · ECU00003435 | 300 | Operational | 2022-02-22 |
Heathland Wind Farm EDF Energy Renewables · ECU00002218 · 12.5 mo to decide | — | Awaiting Construction | 2022-02-09 |
Hunterston Grid Services Complex - Energy Storage Facility Amp Energy · ECU00003319 · 4.8 mo to decide | 400 | Awaiting Construction | 2022-01-05 |
Kincardine Grid Services Complex - Energy Storage Facility Amp Energy · ECU00003326 · 4.6 mo to decide | 400 | Awaiting Construction | 2022-01-05 |
Dersalloch Battery Storage Facility Scottish Power Renewables (UK) Limited · ECU00002112 · 15.9 mo to decide | 50 | Awaiting Construction | 2021-11-29 |
Stranoch 2 EDF Energy · ECU00000710 · 37.2 mo to decide | 20 | Under Construction | 2021-11-24 |
Douglas West Wind Farm (extension) ScottishPower Renewables (UK) Limited · ECU00001836 · 31.2 mo to decide | 20 | Under Construction | 2021-11-18 |
Cumberhead West Wind Farm 3R Energy Solutions Limited · ECU00002171 · 11.5 mo to decide | 40 | Under Construction | 2021-11-18 |
Arecleoch Wind Farm (extension) ScottishPower Renewables · ECU00001864 · 29.2 mo to decide | 20 | Under Construction | 2021-11-16 |
Daer Wind Farm E.ON Climate & Renewables UK Developments · ECU00000740 | 100 | Application Submitted | 2021-05-26 |
Troston Loch Wind Farm EDF Energy Renewables · ECU00001785 · 21.9 mo to decide | 20 | Awaiting Construction | 2020-12-18 |
Euchanhead Wind Farm ScottishPower Renewables UK Limited · �ECU00002141 | — | Application Submitted | 2020-11-30 |
Hopsrig Wind Farm Muirhall Energy Limited · ECU00002160 | 14.1 | Application Submitted | 2020-10-23 |
High Constellation Wind Farm BayWa r.e. UK Limited · ECU00001857 · 13 mo to decide | 55.5 | Awaiting Construction | 2020-06-26 |
Hagshaw Hill Scottish Power Renewables · ECU00000737 · 14.8 mo to decide | 20 | Awaiting Construction | 2020-02-26 |
Harestanes Windfarm ScottishPower Renewables · ECU00001870 · 6 mo to decide | 100 | Under Construction | 2019-12-20 |
Sheirdrim Renewable Energy Development - Battery ScottishPower Renewables · ECU00001957 | 38 | Appeal Refused | 2019-10-10 |
Whitelee Wind Farm Battery Storage Extension Scottish Power Renewables (formerly Arcus Consultancy Services) · ECU00000729 · 4.3 mo to decide | 50 | Operational | 2019-06-10 |
Douglas West Wind Farm (extension) Douglas West Extension / 3R Energy Solutions · ECU00001836 | 20 | Application Submitted | 2019-04-12 |
Whitelaw Brae Wind farm Thrive Renewables · EC00002090 · 35.9 mo to decide | 4 | Awaiting Construction | 2017-12-07 |
Does Scottish Government (S36) approve battery storage schemes?
Yes — of the 108 battery storage schemes Scottish Government (S36) has decided, 94% were approved (102 granted, 6 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in Scottish Government (S36)?
The median time from application to decision is 17.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Scottish Government (S36) consented?
17,631 MW has been consented across 102 approved schemes, with 118 MW refused. A further 105 applications awaits a decision.
Other technologies in Scottish Government (S36)
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com
Screen a specific site here · All authorities · UK property report