Battery storage planning in North Ayrshire

North Ayrshire has decided 6 battery storage schemes and approved 100% of them, taking a median of 7 months to decide. Consented capacity: 110 MW. 1 application still awaiting a decision.

100%
Approved
6 granted · 0 refused
7 mo
Median decision
UK 6 mo
110 MW
Consented
across approved schemes
1
Appeals
1 allowed on appeal

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How North Ayrshire compares

Against the 137 UK authorities with 5+ battery storage decisions, North Ayrshire sits in the 73rd percentile for approval rate (8 points above the England average) and the 34th percentile for speed.

Decisions by year

35Approved — 1 (2021)121Approved — 3 (2023)323Approved — 1 (2024)124Approved — 1 (2025)125
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (8)

SchemeMWStatusDecided
Ardoch Farm
Capbal · 24/00941/PPM · 2.3 mo to decide
20Awaiting Construction2025-03-19
Wee Minnemoer, Millport - Solar Farm & Battery Storage
Comsol Energy · 23/00114/PP · 11.7 mo to decide
Awaiting Construction2024-02-09
Meiklelaught Farm - Battery Storage
Green Power Consultants · 23/00731/PPM · 2 mo to decide
30Awaiting Construction2023-12-13
Tofts - Battery Storage
Telford Three Limited · 23/00396/PPP · 2.3 mo to decide
19.9Awaiting Construction2023-09-14
Wardlaw Wood Windfarm - Battery Storage
Community Windpower Limited · 23/00593/PP · 1.1 mo to decide
19.99Awaiting Construction2023-09-07
North West Of Jameston Farm
Private Developer · 21/00689/MSC · 34.8 mo to decide
19.9Awaiting Construction2021-09-21
Ardoch Farm
Capbal · 18/00445/PPP · 38.4 mo to decide
20Revised2021-07-30
Hunterston
Scottish Enterprise/SSE · 08/00576/PPP · 32.2 mo to decide
5Abandoned2011-03-23

Does North Ayrshire approve battery storage schemes?

Yes — of the 6 battery storage schemes North Ayrshire has decided, 100% were approved (6 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in North Ayrshire?

The median time from application to decision is 7 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has North Ayrshire consented?

110 MW has been consented across 6 approved schemes. A further 1 application awaits a decision.

Other technologies in North Ayrshire

Solar in North AyrshireOnshore wind in North Ayrshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.