Renewable sitesWestfield

Westfield

Westfield is an operational 10 MW onshore wind farm in Fife, generating since 31 March 2013. Planning permission was granted on 22 June 2012, 35 months after submission. Operator of record: Ventient (formerly Infinis).

10 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2013
Wind Onshore
Technology
Ventient (formerly Infinis)
Fife
Authority
Scotland

Planning and build timeline

Application submitted31 July 2009
Permission granted22 June 2012
35 months after submission
Operational31 March 2013
9 months after consent

Screening a site of your own?

RedlineUK · £39

Fife approves 54% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Westfield’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Fife’s record on onshore wind

Fife has decided 28 onshore wind schemes and approved 54%, taking a median of 16.1 months. See every onshore wind scheme decision in Fife

Other built sites within 15 km

SiteMWDistance
Biomass (dedicated) · Operational
12.50.7 km
EfW Incineration · Under Construction
23.72.2 km
Wind Onshore · Operational
253.9 km
Wind Onshore · Operational
6.94 km
Battery · Operational
49.994.4 km
Solar Photovoltaics · Operational
0.35.4 km
Wind Onshore · Operational
4.66.3 km
Anaerobic Digestion · Operational
26.3 km

How big is Westfield?

Westfield has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Westfield?

REPD records the operator as Ventient (formerly Infinis). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Westfield approved and built?

The application was submitted on 31 July 2009. Permission was granted on 22 June 2012, 35 months later. The site became operational on 31 March 2013, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3684.