Clentrie Wind Farm (Gevens)
Clentrie Wind Farm (Gevens) is an operational 6.9 MW onshore wind farm in Fife, generating since 24 October 2016. Planning permission was granted on 15 May 2014, 32 months after submission. Operator of record: Rev Ltd.
Planning and build timeline
| Application submitted | 22 September 2011 |
| Permission granted | 15 May 2014 32 months after submission |
| Operational | 24 October 2016 29 months after consent |
Screening a site of your own?
Fife approves 54% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Clentrie Wind Farm (Gevens)’s recorded coordinate — swap in your own postcode or coordinates.
Fife’s record on onshore wind
Fife has decided 28 onshore wind schemes and approved 54%, taking a median of 16.1 months. See every onshore wind scheme decision in Fife →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 25 | 0.2 km |
Battery · Operational | 49.99 | 1.3 km |
EfW Incineration · Under Construction | 23.7 | 3.6 km |
Wind Onshore · Operational | 10 | 4 km |
Biomass (dedicated) · Operational | 12.5 | 4.2 km |
Wind Onshore · Operational | 4.6 | 5.1 km |
Wind Onshore · Operational | 2 | 5.5 km |
Solar Photovoltaics · Operational | 0.65 | 6.5 km |
How big is Clentrie Wind Farm (Gevens)?
Clentrie Wind Farm (Gevens) has a recorded installed capacity of 6.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Clentrie Wind Farm (Gevens)?
REPD records the operator as Rev Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Clentrie Wind Farm (Gevens) approved and built?
The application was submitted on 22 September 2011. Permission was granted on 15 May 2014, 32 months later. The site became operational on 24 October 2016, 29 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4078.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode