Clentrie Wind Farm (Gevens)

Clentrie Wind Farm (Gevens) is an operational 6.9 MW onshore wind farm in Fife, generating since 24 October 2016. Planning permission was granted on 15 May 2014, 32 months after submission. Operator of record: Rev Ltd.

6.9 MW
Capacity
as recorded in REPD
Operational
Status
since 24 October 2016
Wind Onshore
Technology
Rev Ltd
Fife
Authority
Scotland

Planning and build timeline

Application submitted22 September 2011
Permission granted15 May 2014
32 months after submission
Operational24 October 2016
29 months after consent

Screening a site of your own?

RedlineUK · £39

Fife approves 54% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Clentrie Wind Farm (Gevens)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Fife’s record on onshore wind

Fife has decided 28 onshore wind schemes and approved 54%, taking a median of 16.1 months. See every onshore wind scheme decision in Fife

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
250.2 km
Battery · Operational
49.991.3 km
EfW Incineration · Under Construction
23.73.6 km
Wind Onshore · Operational
104 km
Biomass (dedicated) · Operational
12.54.2 km
Wind Onshore · Operational
4.65.1 km
Wind Onshore · Operational
25.5 km
Solar Photovoltaics · Operational
0.656.5 km

How big is Clentrie Wind Farm (Gevens)?

Clentrie Wind Farm (Gevens) has a recorded installed capacity of 6.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Clentrie Wind Farm (Gevens)?

REPD records the operator as Rev Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Clentrie Wind Farm (Gevens) approved and built?

The application was submitted on 22 September 2011. Permission was granted on 15 May 2014, 32 months later. The site became operational on 24 October 2016, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4078.