Renewable sites › Clentrie Wind Farm (Gevens)
Clentrie Wind Farm (Gevens)
Clentrie Wind Farm (Gevens) is operational in Fife with a recorded capacity of 6.9 MW, and has been generating since 2016-10-24.
Planning and build timeline
| Application submitted | 2011-09-22 |
| Permission granted | 2014-05-15 32 months after submission |
| Operational | 2016-10-24 29 months after consent |
Fife’s record on onshore wind
Fife has decided 28 onshore wind schemes and approved 54%, taking a median of 16.1 months. See every onshore wind scheme decision in Fife →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Little Raith Farm Wind Onshore · Operational | 25 | 0.2 km |
Camilla Battery Storage Battery · Operational | 49.99 | 1.3 km |
Westfield (former Opencast Coal Mine) EfW Incineration · Under Construction | 23.7 | 3.6 km |
Westfield Wind Onshore · Operational | 10 | 4 km |
Westfield Biomass Power Station Biomass (dedicated) · Operational | 12.5 | 4.2 km |
Mossmorran Wind Farm Wind Onshore · Operational | 4.6 | 5.1 km |
Goathill Quarry Turbine Wind Onshore · Operational | 2 | 5.5 km |
Kirkcaldy W W T W, Nether Street- Solar Panels Solar Photovoltaics · Operational | 0.65 | 6.5 km |
How big is Clentrie Wind Farm (Gevens)?
Clentrie Wind Farm (Gevens) has a recorded installed capacity of 6.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Clentrie Wind Farm (Gevens)?
REPD records the operator as Rev Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Clentrie Wind Farm (Gevens) approved and built?
The application was submitted on 2011-09-22. Permission was granted on 2014-05-15, 32 months later. The site became operational on 2016-10-24, 29 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4078.
Novarly Parcel · official public data, read properly · parcel.novarly.com