Finmont Service Reservoir
Finmont Service Reservoir is an operational 0.3 MW solar farm in Fife, generating since 23 July 2020. Planning permission was granted on 13 September 2019, 9 months after submission. Operator of record: Scottish Water.
Planning and build timeline
| Application submitted | 11 December 2018 |
| Permission granted | 13 September 2019 9 months after submission |
| Operational | 23 July 2020 10 months after consent |
Screening a site of your own?
Fife approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Finmont Service Reservoir’s recorded coordinate — swap in your own postcode or coordinates.
Fife’s record on solar
Fife has decided 31 solar farms and approved 100%, taking a median of 3.7 months. See every solar farm decision in Fife →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Anaerobic Digestion · Operational | 2 | 1.7 km |
Battery · Under Construction | 19.9 | 3.6 km |
Battery · Under Construction | — | 3.8 km |
EfW Incineration · Under Construction | 23.7 | 3.9 km |
Biomass (dedicated) · Operational | 65 | 5.2 km |
Wind Onshore · Operational | 1.5 | 5.2 km |
Wind Onshore · Operational | 1.5 | 5.3 km |
Wind Onshore · Operational | 10 | 5.4 km |
How big is Finmont Service Reservoir?
Finmont Service Reservoir has a recorded installed capacity of 0.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Finmont Service Reservoir?
REPD records the operator as Scottish Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Finmont Service Reservoir approved and built?
The application was submitted on 11 December 2018. Permission was granted on 13 September 2019, 9 months later. The site became operational on 23 July 2020, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6745.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode