Renewable sites › Camilla Battery Storage
Camilla Battery Storage
Camilla Battery Storage is an operational 49.99 MW battery storage site in Fife, generating since 20 March 2024. Planning permission was granted on 22 October 2022, 26 months after submission. Operator of record: NextEnergy Solar Fund / Eelpower Limited.
Planning and build timeline
| Application submitted | 26 August 2020 |
| Permission granted | 22 October 2022 26 months after submission |
| Operational | 20 March 2024 17 months after consent |
Screening a site of your own?
Fife approves 96% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Camilla Battery Storage’s recorded coordinate — swap in your own postcode or coordinates.
Fife’s record on battery storage
Fife has decided 23 battery storage schemes and approved 96%, taking a median of 3.9 months. See every battery storage scheme decision in Fife →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 6.9 | 1.3 km |
Wind Onshore · Operational | 25 | 1.4 km |
Wind Onshore · Operational | 4.6 | 3.8 km |
Wind Onshore · Operational | 2 | 4.2 km |
Biomass (dedicated) · Operational | 12.5 | 4.4 km |
Wind Onshore · Operational | 10 | 4.4 km |
EfW Incineration · Under Construction | 23.7 | 4.5 km |
Solar Photovoltaics · Operational | 0.65 | 7.4 km |
How big is Camilla Battery Storage?
Camilla Battery Storage has a recorded installed capacity of 49.99 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Camilla Battery Storage?
REPD records the operator as NextEnergy Solar Fund / Eelpower Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Camilla Battery Storage approved and built?
The application was submitted on 26 August 2020. Permission was granted on 22 October 2022, 26 months later. The site became operational on 20 March 2024, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 16075.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode