Renewable sites › Camilla Battery Storage
Camilla Battery Storage
Camilla Battery Storage is operational in Fife with a recorded capacity of 49.99 MW, and has been generating since 2024-03-20.
Planning and build timeline
| Application submitted | 2020-08-26 |
| Permission granted | 2022-10-22 26 months after submission |
| Operational | 2024-03-20 17 months after consent |
Fife’s record on battery storage
Fife has decided 23 battery storage schemes and approved 96%, taking a median of 3.9 months. See every battery storage scheme decision in Fife →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Clentrie Wind Farm (Gevens) Wind Onshore · Operational | 6.9 | 1.3 km |
Little Raith Farm Wind Onshore · Operational | 25 | 1.4 km |
Mossmorran Wind Farm Wind Onshore · Operational | 4.6 | 3.8 km |
Goathill Quarry Turbine Wind Onshore · Operational | 2 | 4.2 km |
Westfield Biomass Power Station Biomass (dedicated) · Operational | 12.5 | 4.4 km |
Westfield Wind Onshore · Operational | 10 | 4.4 km |
Westfield (former Opencast Coal Mine) EfW Incineration · Under Construction | 23.7 | 4.5 km |
Kirkcaldy W W T W, Nether Street- Solar Panels Solar Photovoltaics · Operational | 0.65 | 7.4 km |
How big is Camilla Battery Storage?
Camilla Battery Storage has a recorded installed capacity of 49.99 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Camilla Battery Storage?
REPD records the operator as NextEnergy Solar Fund / Eelpower Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Camilla Battery Storage approved and built?
The application was submitted on 2020-08-26. Permission was granted on 2022-10-22, 26 months later. The site became operational on 2024-03-20, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 16075.