Novarly ParcelRenewable sites

Renewable sitesInchdairnie

Inchdairnie

Inchdairnie is an operational 2 MW anaerobic digestion plant in Fife, generating since 1 June 2018. Planning permission was granted on 15 July 2016, 9 months after submission. Operator of record: RM Brown & Son Ltd.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 1 June 2018
Anaerobic Digestion
Technology
RM Brown & Son Ltd
Fife
Authority
Scotland

Planning and build timeline

Application submitted28 October 2015
Permission granted15 July 2016
9 months after submission
Operational1 June 2018
23 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Fife: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Inchdairnie’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.31.7 km
Battery · Under Construction
19.93.3 km
Wind Onshore · Operational
1.53.5 km
Wind Onshore · Operational
1.53.6 km
Battery · Under Construction
3.9 km
Biomass (dedicated) · Operational
654 km
Wind Onshore · Operational
6.44 km
Solar Photovoltaics · Operational
54 km

How big is Inchdairnie?

Inchdairnie has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Inchdairnie?

REPD records the operator as RM Brown & Son Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Inchdairnie approved and built?

The application was submitted on 28 October 2015. Permission was granted on 15 July 2016, 9 months later. The site became operational on 1 June 2018, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5899.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode