Little Raith Farm

Little Raith Farm is operational in Fife with a recorded capacity of 25 MW, and has been generating since 2012-11-27.

25 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-11-27
Wind Onshore
Technology
Renewables Infrastructure Group
Fife
Authority
Scotland

Planning and build timeline

Application submitted2004-12-02
Permission granted2007-03-08
27 months after submission
Operational2012-11-27
69 months after consent

Fife’s record on onshore wind

Fife has decided 28 onshore wind schemes and approved 54%, taking a median of 16.1 months. See every onshore wind scheme decision in Fife

Other built sites within 15 km

SiteMWDistance
Clentrie Wind Farm (Gevens)
Wind Onshore · Operational
6.90.2 km
Camilla Battery Storage
Battery · Operational
49.991.4 km
Westfield (former Opencast Coal Mine)
EfW Incineration · Under Construction
23.73.4 km
Westfield
Wind Onshore · Operational
103.9 km
Westfield Biomass Power Station
Biomass (dedicated) · Operational
12.54.1 km
Mossmorran Wind Farm
Wind Onshore · Operational
4.65.2 km
Goathill Quarry Turbine
Wind Onshore · Operational
25.6 km
Kirkcaldy W W T W, Nether Street- Solar Panels
Solar Photovoltaics · Operational
0.656.4 km

How big is Little Raith Farm?

Little Raith Farm has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Little Raith Farm?

REPD records the operator as Renewables Infrastructure Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Little Raith Farm approved and built?

The application was submitted on 2004-12-02. Permission was granted on 2007-03-08, 27 months later. The site became operational on 2012-11-27, 69 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4034.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council