Consent Clock: permissions granted, schemes not built

39.9 GW of consented UK renewable capacity, across 2,113 schemes, is still recorded as awaiting construction more than 3 years after permission was granted — 29% of the whole consented-but-unbuilt pipeline. Another 9.8 GW reaches the three-year point inside the next six months.

139.2 GW
Consented, unbuilt
5,562 schemes
39.9 GW
Past 3 years
2,113 schemes
9.8 GW
Crosses it within 6 months
646 schemes

These are not expired permissions

A permission past its commencement date has not necessarily lapsed. REPD records neither the commencement condition on the decision notice nor whether a material operation has begun — and once development lawfully begins, the permission is implemented and stops expiring. Large schemes are frequently given five years rather than three. DESNZ also records a separate Planning Permission Expired status, so every scheme counted here is one it has not marked expired. Read this as a list of consents worth checking against the decision notice, never as a list of consents that have gone.

How long consents have been sitting

Time since consentSchemesCapacity
Consented over 5 years ago
Past even a five-year commencement condition. Either implemented, extended, or lapsed.
38612.0 GW
Consented 3 to 5 years ago
Past a standard three-year condition, but inside a five-year one.
1,72727.8 GW
Reaches 3 years within 6 months
The window where a developer would normally either start work or apply to extend.
6469.8 GW
Reaches 3 years in 6 to 12 months
Far enough out that a decision to build, sell or extend is still open.
6719.1 GW
Consented under 2 years ago
Comfortably inside the commencement period.
2,13280.4 GW

By technology

TechnologyConsented, unbuiltPast 3 yrsWithin 6 mo
Solar24.2 GW · 3,7058.1 GW · 1,4212.0 GW · 493
Battery storage67.8 GW · 1,23111.8 GW · 3416.3 GW · 106
Onshore wind7.3 GW · 3483.6 GW · 194687 MW · 20

Where the unbuilt capacity sits

Authorities holding the most consented capacity granted over 3 years ago and still awaiting construction.

AuthoritySchemesCapacity
The Planning Inspectorate - National Infrastructure · England1911.4 GW
Scottish Government (S36) · Scotland486.5 GW
Marine Scotland · Scotland41.7 GW
North Yorkshire · England491.2 GW
Trafford · England71.1 GW
South Holland · England12556 MW
South Norfolk · England12550 MW
Aberdeenshire · Scotland38510 MW
Wiltshire · England30510 MW
King's Lynn and West Norfolk · England14469 MW
Thurrock · England4452 MW
Highland · Scotland24434 MW
East Riding of Yorkshire · England30407 MW
South Cambridgeshire · England7373 MW
Lancaster · England8356 MW

Largest consents past the 3-year point

SchemeMWConsented
Hornsea 3
Orsted (formerly Dong Energy) · The Planning Inspectorate - National Infrastructure · Wind Offshore
29552020-12-30
5 yr 6 mo ago
Hornsea 4
Orsted (formerly Dong Energy) · The Planning Inspectorate - National Infrastructure · Wind Offshore
26002023-07-12
3 yr 0 mo ago
Coire Glas
SSE Renewables · Scottish Government (S36) · Pumped Storage Hydroelectricity
15002020-10-15
5 yr 9 mo ago
The East Anglia Array - Norfolk Vanguard East
RWE Renewables UK Limited · The Planning Inspectorate - National Infrastructure · Wind Offshore
13802022-02-11
4 yr 5 mo ago
The East Anglia Array - Norfolk Vanguard West
RWE Renewables UK Limited · The Planning Inspectorate - National Infrastructure · Wind Offshore
13802022-02-11
4 yr 5 mo ago
Inch Cape
Red Rock Power (ICOL) · Marine Scotland · Wind Offshore
10802017-05-16
9 yr 2 mo ago
Carrington Power Station, Manchester Road - Battery Storage
Wainstones Energy Limited · Trafford · Battery
10402023-07-20
3 yr 0 mo ago
East Anglia 2 (EA 2)
Scottish Power Renewables · The Planning Inspectorate - National Infrastructure · Wind Offshore
9002022-03-31
4 yr 3 mo ago
East Anglia 1 North (EA 4)
Scottish Power Renewables · The Planning Inspectorate - National Infrastructure · Wind Offshore
8002022-03-31
4 yr 3 mo ago
Cruachan Hydro Expansion
Drax Power Limited / Stantec UK · Scottish Government (S36) · Pumped Storage Hydroelectricity
6002023-07-21
3 yr 0 mo ago
Spalding Energy Park - Battery Storage
Intergen Limited · South Holland · Battery
5502023-06-14
3 yr 1 mo ago
Seagreen Phase 1A
SSE / Seagreen Wind Energy Ltd · Marine Scotland · Wind Offshore
5402019-12-06
6 yr 7 mo ago
Longfield
Longfield Solar Energy Farm Limited (part of EDF Renwables) · The Planning Inspectorate - National Infrastructure · Solar Photovoltaics
5002023-06-26
3 yr 1 mo ago
Eggborough Power Station, Selby Road - Battery Storage
Eggborough Power Limited · North Yorkshire · Battery
5002023-01-17
3 yr 6 mo ago
Red John Pumped Storage
Statkraft · Scottish Government (S36) · Pumped Storage Hydroelectricity
4502021-06-07
5 yr 1 mo ago
Gateway Energy Centre - Battery Energy Storage
Intergen Limited · Thurrock · Battery
4502023-01-13
3 yr 6 mo ago
Glenmuckloch Pumped Storage Hydro
Buccleuch Estates · Scottish Government (S36) · Pumped Storage Hydroelectricity
4002016-11-29
9 yr 7 mo ago
Kincardine Grid Services Complex - Energy Storage Facility
Amp Energy · Scottish Government (S36) · Battery
4002022-01-05
4 yr 6 mo ago
Hunterston Grid Services Complex - Energy Storage Facility
Amp Energy · Scottish Government (S36) · Battery
4002022-01-05
4 yr 6 mo ago
Stargoose Farm - Battery Storage
Solarcentury Limited / Statkraft Uk Limited · South Cambridgeshire · Battery
3122022-04-14
4 yr 3 mo ago

Reaching 3 years within six months

The largest consents now inside the window where a scheme on a standard condition would need to start work, apply to extend, or be sold.

SchemeMWConsented
Coalburn II Energy Storage Facility - Battery Storage Facility
Alcemi Storage Development Limited · Scottish Government (S36) · Battery
10002024-01-24
30 months ago
Fanny House Farm, Bay Gateway - Battery Storage
Innova Renewables · Lancaster · Battery
9402023-11-28
31 months ago
Awel y Mor Offshore Wind Farm
RWE Renewables · The Planning Inspectorate - National Infrastructure · Wind Offshore
7752023-09-20
34 months ago
Normanton Energy Reserve - Battery Storage
Exagen SPVO2 Limited · Blaby · Battery
5002024-01-16
30 months ago
Blackdyke Farm, Blackford - Battery Storage
Innova Renewables · Cumberland · Battery
4002023-10-05
33 months ago
Camsiscan Farm, Craigie - Battery Energy Storage System
Noriker Power Limited · Scottish Government (S36) · Battery
3502024-01-26
30 months ago
Penrhos Works - Battery Energy Storage System
Anglesey Land Holdings Limited · Isle of Anglesey · Battery
3492024-01-24
30 months ago
Saundercroft Farm - Battery Energy Storage System
Exeter Storage Limited (Statera Energy) · East Devon · Battery
2902024-01-12
30 months ago
Printworks Road - Stalybridge Battery Storage
Zenobe Energy · Tameside · Battery
1502023-12-15
31 months ago
Wilton International, Greystones Road - Phase 1
Sembcorp Utilities (UK) Limited · Redcar and Cleveland · Battery
1502023-10-04
33 months ago
Clough Road - Battery Energy System
GAM Capital Limited · Kingston upon Hull, City of · Battery
1302023-09-12
34 months ago
Energy Isles Wind Farm
Energy Isles / Stratcraft · Scottish Government (S36) · Wind Onshore
1262023-10-02
33 months ago

Does a planning permission expire if the developer never starts?

In England, Wales and Scotland a planning permission normally carries a condition requiring development to begin within 3 years. If a material operation has not begun by then, the permission lapses and a fresh application is needed. The period is a default, not a rule: a decision notice can set a longer one, and five years is common on large or phased schemes. Once development has lawfully begun the permission is implemented and no longer expires.

How much consented UK renewable capacity is sitting unbuilt?

139.2 GW across 5,562 schemes is recorded in REPD as consented and awaiting construction. Of that, 39.9 GW across 2,113 schemes was granted more than 3 years ago — 29% of the consented-but-unbuilt pipeline by capacity. A further 9.8 GW reaches the three-year point within six months.

Does this mean those permissions have expired?

No, and this page does not claim it. REPD does not record the commencement condition on a decision notice, and it does not record whether a material operation has begun — so a scheme past three years may have been implemented, may have been given a longer period, or may have had the permission extended. DESNZ separately records a "Planning Permission Expired" status, so everything counted here is a scheme it has not marked expired. Treat the list as consents worth checking, not consents that have lapsed.

Why would a developer hold a consent and not build?

Most commonly the grid connection date sits years beyond the planning consent, so the scheme is consented but cannot physically energise yet. Others are waiting on a power purchase agreement or a CfD allocation round, are being marketed for sale as a consented asset, or were consented speculatively to establish value in the land. A consent nearing its commencement deadline is the point at which the owner has to start work, apply to extend, sell, or lose it.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0. Counts cover schemes recorded as Awaiting Construction with a recorded grant date, of roughly 150 kW and above. REPD is published quarterly, so a status can be several months behind reality. Capacity is installed capacity as recorded. Screening context for site selection and pipeline research, not planning advice.