Onshore wind planning in Fife

Fife has decided 28 onshore wind schemes and approved 54% of them, taking a median of 16.1 months to decide. Consented capacity: 94 MW. 3 applications still awaiting a decision.

54%
Approved
15 granted · 13 refused
16.1 mo
Median decision
UK 11.5 mo
94 MW
Consented
174 MW refused
9
Appeals
2 allowed on appeal

How Fife compares

Against the 75 UK authorities with 5+ onshore wind decisions, Fife sits in the 23rd percentile for approval rate (14 points below the England average) and the 33rd percentile for speed.

Decisions by year

35Approved — 1 (2011)Refused — 1 (2011)211Approved — 3 (2012)Refused — 2 (2012)512Approved — 2 (2013)Refused — 2 (2013)413Approved — 3 (2014)Refused — 2 (2014)514Refused — 1 (2015)115Approved — 1 (2016)Refused — 1 (2016)216Refused — 1 (2018)118Approved — 1 (2022)122Approved — 1 (2024)124
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (36)

SchemeMWStatusDecided
Kirkmay Farm, Crail - Wind Turbine
R.F Logan & Co · 24/02680/FULL · 2 mo to decide
0.22Awaiting Construction2024-12-11
Kirkton Barns Farm - Wind Turbine
Kirkton Barns Farm · 23/02605/FULL
0.23Application Withdrawn2024-02-23
Saline Shaw - Wind Turbine
Private Developer · 22/00341/FULL · 3 mo to decide
0.5Awaiting Construction2022-05-05
Easter Muirhead Farm
ABO Wind UK · 09/01359/WEIA · 112.2 mo to decide
15Application Refused2018-10-19
Blairadam Wind Farm
Partnerships for Renewables Development Company Limited · 14/00008/EIA · 33.1 mo to decide
22.6Application Refused2016-10-27
Kenly Wind Farm
University of St Andrews · 16/01425/EIA · 4.1 mo to decide
12.3Awaiting Construction2016-08-25
Little Raith Farm - extension
WK Extension Project Ltd · 14/02444/EIA · 11.4 mo to decide
18Appeal Refused2015-06-30
Wester Durie Farm
Ore Valley Housing Association · 13/03643/EIA · 8.5 mo to decide
2.3Application Refused2014-08-22
Cuddyhouse Road
Midland Solar Grid · 14/00374/FULL
1.5Application Withdrawn2014-06-19
Clentrie Wind Farm (Gevens)
Rev Ltd · 11/04794/EIA · 31.7 mo to decide
6.9Operational2014-05-15
Outh Muir Wind Farm
REG Windpower · 13/01898/EIA · 8.8 mo to decide
12.5Appeal Refused2014-03-27
J2a
Airvolution Energy · 14/00316/EIA
4.7Abandoned2014-01-31
Middle Balbeggie Wind Turbines
Capital Dynamics · 12/04094/EIA · 16 mo to decide
6.4Operational2014-01-29
Skeddoway Farm Wind Turbine
Clenergy · 13/00269/EIA · 11.1 mo to decide
1.5Operational2014-01-09
Mossmorran Wind Farm
Airvolution Energy · 12/02692/FULL
6Application Withdrawn2013-11-19
Troywood Wind Turbine
Private Developer · 09/02880/FULL
2.3Application Withdrawn2013-10-08
Kenly Wind Farm (University of St Andrew's)
University of St Andrews · 11/02799/EIA · 27.6 mo to decide
13.8Revised2013-10-07
Kingdom of Fife Community Wind Park
Atmos Consulting Ltd · 11/03990/EIA · 26.2 mo to decide
12Application Refused2013-10-01
Goathill Quarry Turbine
Collier Quarrying Group · 11/05591/EIA · 19.6 mo to decide
2Operational2013-06-21
Bonerbo Wind Turbines
Messrs Stevenson, Watson and Brunton · 12/02748/FULL · 10.1 mo to decide
1.5Operational2013-05-14
Skeddoway Farm Wind Turbine
RM Brown & Son Ltd · 11/04896/FULL · 16.2 mo to decide
1.5Revised2013-02-01
Lingo Wind Farm
Lingo Wind Energy Ltd · 12/00129/EIA · 12.3 mo to decide
12.5Appeal Refused2013-01-31
Westfield
Ventient (formerly Infinis) · 09/01861/EIA · 34.7 mo to decide
10Operational2012-06-22
Clatto Farm Turbines
Green Cat Renewables · 10/01469/EIA · 23 mo to decide
6Appeal Refused2012-04-18
Devon Wood
East Fife Wind Energy · 10/02183/EIA · 21.6 mo to decide
12.5Appeal Refused2012-04-18
Earlseat
The Renewables Infrastructure Group (TRIG) · 10/03539/EIA · 17.5 mo to decide
18.4Operational2012-03-02
Bonerbo Wind Turbines
Messrs Stevenson, Watson and Brunton · 12/00482/FULL
2.7Revised2012-02-28
Mossmorran Wind Farm
Airvolution Energy · 11/01807/FULL · 9.4 mo to decide
4.6Operational2012-01-13
South Cassingray
Private Developer · 10/02616/FULL · 17 mo to decide
4.6Appeal Refused2011-12-21
Noble Foods
Wind Direct · 11/02164/FULL · 6.2 mo to decide
1.5Operational2011-11-15
FMC Technologies
FMC Technologies · 09/00301/WFULL · 10.3 mo to decide
1.5Operational2009-12-22
F M C Land, Pitreavie Business Park
FMC Corp UK Ltd · 09/00301/WFUL · 10.2 mo to decide
1.5Operational2009-12-22
Gathercauld
Energiekontor UK · 07/01813/EEIA · 24.5 mo to decide
15.6Application Refused2009-06-17
Auchtermuchty Wind Farm
Energiekontor UK · 19 mo to decide
10Application Refused2008-01-01
Little Raith Farm
Renewables Infrastructure Group · 04/04266/WEIA · 27.1 mo to decide
25Operational2007-03-08
Clatto
Scottish Power Renewables · 03/03397/EEIA · 13.3 mo to decide
30Application Refused2004-11-01

Does Fife approve onshore wind schemes?

Yes — of the 28 onshore wind schemes Fife has decided, 54% were approved (15 granted, 13 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Fife?

The median time from application to decision is 16.1 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Fife consented?

94 MW has been consented across 15 approved schemes, with 174 MW refused. A further 3 applications awaits a decision.

Other technologies in Fife

Solar in FifeBattery storage in Fife

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.