Renewable sitesWestfield Biomass Power Station

Westfield Biomass Power Station

Westfield Biomass Power Station is an operational 12.5 MW biomass plant in Fife, generating since 21 August 2000. Planning permission was granted on 5 December 1995, 21 months after submission. Operator of record: EPR Scotland.

12.5 MW
Capacity
as recorded in REPD
Operational
Status
since 21 August 2000
Biomass (dedicated)
Technology
EPR Scotland
Fife
Authority
Scotland

Planning and build timeline

Application submitted3 March 1994
Permission granted5 December 1995
21 months after submission
Operational21 August 2000
57 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Fife: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Westfield Biomass Power Station’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
100.7 km
EfW Incineration · Under Construction
23.72.9 km
Wind Onshore · Operational
254.1 km
Wind Onshore · Operational
6.94.2 km
Battery · Operational
49.994.4 km
Wind Onshore · Operational
4.65.8 km
Solar Photovoltaics · Operational
0.36.1 km
Wind Onshore · Operational
26.2 km

How big is Westfield Biomass Power Station?

Westfield Biomass Power Station has a recorded installed capacity of 12.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Westfield Biomass Power Station?

REPD records the operator as EPR Scotland. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Westfield Biomass Power Station approved and built?

The application was submitted on 3 March 1994. Permission was granted on 5 December 1995, 21 months later. The site became operational on 21 August 2000, 57 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 62.