Westfield Biomass Power Station is operational in Fife with a recorded capacity of 12.5 MW, and has been generating since 2000-08-21.

12.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2000-08-21
Biomass (dedicated)
Technology
EPR Scotland
Fife
Authority
Scotland

Planning and build timeline

Application submitted1994-03-03
Permission granted1995-12-05
21 months after submission
Operational2000-08-21
57 months after consent

Other built sites within 15 km

SiteMWDistance
Westfield
Wind Onshore · Operational
100.7 km
Westfield (former Opencast Coal Mine)
EfW Incineration · Under Construction
23.72.9 km
Little Raith Farm
Wind Onshore · Operational
254.1 km
Clentrie Wind Farm (Gevens)
Wind Onshore · Operational
6.94.2 km
Camilla Battery Storage
Battery · Operational
49.994.4 km
Mossmorran Wind Farm
Wind Onshore · Operational
4.65.8 km
Finmont Service Reservoir
Solar Photovoltaics · Operational
0.36.1 km
Goathill Quarry Turbine
Wind Onshore · Operational
26.2 km

How big is Westfield Biomass Power Station?

Westfield Biomass Power Station has a recorded installed capacity of 12.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Westfield Biomass Power Station?

REPD records the operator as EPR Scotland. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Westfield Biomass Power Station approved and built?

The application was submitted on 1994-03-03. Permission was granted on 1995-12-05, 21 months later. The site became operational on 2000-08-21, 57 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 62.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council