Pen Bryn Oer Wind Farm is operational in Caerphilly with a recorded capacity of 4 MW, and has been generating since 2018-01-15.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-01-15
Wind Onshore
Technology
REG Windpower/ BlackRock
Caerphilly
Authority
Wales

Planning and build timeline

Application submitted2013-06-28
Permission granted2015-08-06
25 months after submission
Operational2018-01-15
29 months after consent

Caerphilly’s record on onshore wind

Caerphilly has decided 6 onshore wind schemes and approved 50%, taking a median of 3.2 months. See every onshore wind scheme decision in Caerphilly

Other built sites within 15 km

SiteMWDistance
Trecatti
Landfill Gas · Operational
73.6 km
Land At Cwm Bargoed
Solar Photovoltaics · Operational
54.3 km
Rassau Industrial Estate
Battery · Under Construction
64.3 km
Silent Valley Landfill Scheme
Landfill Gas · Operational
2.76.8 km
Hafod-Y-Dafal Farm
Solar Photovoltaics · Operational
149.8 km
Manmoel Road Solar Park
Solar Photovoltaics · Operational
4.110.4 km
Hendai Farm
Solar Photovoltaics · Operational
13.411.2 km
Land at Darran Farm
Solar Photovoltaics · Operational
2.611.7 km

How big is Pen Bryn Oer Wind Farm?

Pen Bryn Oer Wind Farm has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pen Bryn Oer Wind Farm?

REPD records the operator as REG Windpower/ BlackRock. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pen Bryn Oer Wind Farm approved and built?

The application was submitted on 2013-06-28. Permission was granted on 2015-08-06, 25 months later. The site became operational on 2018-01-15, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4412.