Planning and build timeline
| Application submitted | 2013-06-28 |
| Permission granted | 2015-08-06 25 months after submission |
| Operational | 2018-01-15 29 months after consent |
Caerphilly’s record on onshore wind
Caerphilly has decided 6 onshore wind schemes and approved 50%, taking a median of 3.2 months. See every onshore wind scheme decision in Caerphilly →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Trecatti Landfill Gas · Operational | 7 | 3.6 km |
Land At Cwm Bargoed Solar Photovoltaics · Operational | 5 | 4.3 km |
Rassau Industrial Estate Battery · Under Construction | 6 | 4.3 km |
Silent Valley Landfill Scheme Landfill Gas · Operational | 2.7 | 6.8 km |
Hafod-Y-Dafal Farm Solar Photovoltaics · Operational | 14 | 9.8 km |
Manmoel Road Solar Park Solar Photovoltaics · Operational | 4.1 | 10.4 km |
Hendai Farm Solar Photovoltaics · Operational | 13.4 | 11.2 km |
Land at Darran Farm Solar Photovoltaics · Operational | 2.6 | 11.7 km |
How big is Pen Bryn Oer Wind Farm?
Pen Bryn Oer Wind Farm has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Pen Bryn Oer Wind Farm?
REPD records the operator as REG Windpower/ BlackRock. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pen Bryn Oer Wind Farm approved and built?
The application was submitted on 2013-06-28. Permission was granted on 2015-08-06, 25 months later. The site became operational on 2018-01-15, 29 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4412.