Renewable sites › Trecatti
Trecatti
Trecatti is an operational 7 MW landfill gas site in Caerphilly, generating since 30 July 2002. Planning permission was granted on 24 July 1997, 2 months after submission. Operator of record: Biffa.
Planning and build timeline
| Application submitted | 20 May 1997 |
| Permission granted | 24 July 1997 2 months after submission |
| Operational | 30 July 2002 60 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Caerphilly: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Trecatti’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 2.5 km |
Wind Onshore · Operational | 4 | 3.6 km |
Landfill Gas · Operational | 2.7 | 7 km |
Battery · Under Construction | 6 | 7.5 km |
Solar Photovoltaics · Operational | 13.4 | 7.6 km |
Solar Photovoltaics · Operational | 4.1 | 8.3 km |
Solar Photovoltaics · Operational | 14 | 8.7 km |
Anaerobic Digestion · Operational | 1.4 | 8.8 km |
How big is Trecatti?
Trecatti has a recorded installed capacity of 7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Trecatti?
REPD records the operator as Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Trecatti approved and built?
The application was submitted on 20 May 1997. Permission was granted on 24 July 1997, 2 months later. The site became operational on 30 July 2002, 60 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 769.