Onshore wind planning in Caerphilly

Caerphilly has decided 6 onshore wind schemes and approved 50% of them, taking a median of 3.2 months to decide. Consented capacity: 8 MW.

50%
Approved
3 granted · 3 refused
3.2 mo
Median decision
UK 11.5 mo
8 MW
Consented
4 MW refused
3
Appeals
1 allowed on appeal

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Caerphilly compares

Against the 75 UK authorities with 5+ onshore wind decisions, Caerphilly sits in the 20th percentile for approval rate (18 points below the England average) and the 100th percentile for speed.

Decisions by year

35Approved — 1 (2011)111Refused — 1 (2014)114Approved — 1 (2015)115Refused — 1 (2017)117Refused — 1 (2018)118Approved — 1 (2021)121
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (7)

SchemeMWStatusDecided
Pen-Yr-Heol Farm, Hollybush
Infinite Renewables Group Ltd · 21/0083/FULL · 3.7 mo to decide
Awaiting Construction2021-05-24
Pen-Y-Fan Industrial Estate
Sirius Renewable Energy · 17/0864/FULL · 11.1 mo to decide
1.8Application Refused2018-09-13
Penyrheol Las Farm
Private Developer · 17/0218/FULL · 1.8 mo to decide
1Appeal Refused2017-05-18
Pen Bryn Oer Wind Farm
REG Windpower/ BlackRock · 13/0483/FULL · 25.3 mo to decide
4Operational2015-08-06
Land At Pen Y Fan
Clenergy · 15/0388/FULL
1.5Application Withdrawn2015-07-28
Pen yr Heol Las Farm
Private Developer · 14/0622/FULL · 2.1 mo to decide
1Appeal Refused2014-11-25
Oakdale Business Park
Resonance · 11/0552/FULL · 2.6 mo to decide
4Operational2011-10-06

Does Caerphilly approve onshore wind schemes?

Yes — of the 6 onshore wind schemes Caerphilly has decided, 50% were approved (3 granted, 3 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Caerphilly?

The median time from application to decision is 3.2 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Caerphilly consented?

8 MW has been consented across 3 approved schemes, with 4 MW refused. There are no applications currently awaiting a decision.

Other technologies in Caerphilly

Solar in CaerphillyBattery storage in Caerphilly

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.