Novarly ParcelRenewable sites

Renewable sitesHafod-Y-Dafal Farm

Hafod-Y-Dafal Farm

Hafod-Y-Dafal Farm is an operational 14 MW solar farm in Blaenau Gwent, generating since 22 December 2015. Planning permission was granted on 7 November 2014, 6 months after submission. Operator of record: KS SPV53 Ltd.

14 MW
Capacity
as recorded in REPD
Operational
Status
since 22 December 2015
Solar Photovoltaics
Technology
KS SPV53 Ltd
Blaenau Gwent
Authority
Wales

Planning and build timeline

Application submitted16 May 2014
Permission granted7 November 2014
6 months after submission
Operational22 December 2015
13 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Blaenau Gwent: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hafod-Y-Dafal Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
4.12.9 km
Landfill Gas · Operational
2.73.7 km
Wind Onshore · Operational
44.4 km
Solar Photovoltaics · Operational
2.64.4 km
Solar Photovoltaics · Operational
4.96 km
Landfill Gas · Operational
78.7 km
Wind Onshore · Operational
49.8 km
Solar Photovoltaics · Operational
13.410 km

How big is Hafod-Y-Dafal Farm?

Hafod-Y-Dafal Farm has a recorded installed capacity of 14 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hafod-Y-Dafal Farm?

REPD records the operator as KS SPV53 Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hafod-Y-Dafal Farm approved and built?

The application was submitted on 16 May 2014. Permission was granted on 7 November 2014, 6 months later. The site became operational on 22 December 2015, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2176.