Renewable sites › Land at Darran Farm
Land at Darran Farm
Land at Darran Farm is operational in Caerphilly with a recorded capacity of 2.6 MW, and has been generating since 2017-03-30.
Planning and build timeline
| Application submitted | 2014-10-29 |
| Permission granted | 2016-03-10 16 months after submission |
| Operational | 2017-03-30 13 months after consent |
Caerphilly’s record on solar
Caerphilly has decided 7 solar farms and approved 100%, taking a median of 3.5 months. See every solar farm decision in Caerphilly →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Oakdale Business Park Wind Onshore · Operational | 4 | 0.6 km |
Manmoel Road Solar Park Solar Photovoltaics · Operational | 4.1 | 1.7 km |
Upper Pant-Ysgawen Farm/Crumlin Solar Photovoltaics · Operational | 4.9 | 2.7 km |
Hafod-Y-Dafal Farm Solar Photovoltaics · Operational | 14 | 4.4 km |
Cwmcaesingrug Farm Solar Photovoltaics · Operational | 10 | 6 km |
Penrhiwarwydd Farm Solar Photovoltaics · Operational | 8.5 | 6.4 km |
Gelliargwellt Uchaf Farm AD Anaerobic Digestion · Operational | 1.4 | 6.7 km |
Hendai Farm Solar Photovoltaics · Operational | 13.4 | 6.8 km |
How big is Land at Darran Farm?
Land at Darran Farm has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land at Darran Farm?
REPD records the operator as SRE (Darran). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land at Darran Farm approved and built?
The application was submitted on 2014-10-29. Permission was granted on 2016-03-10, 16 months later. The site became operational on 2017-03-30, 13 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4734.