Renewable sitesManmoel Road Solar Park

Manmoel Road Solar Park

Manmoel Road Solar Park is operational in Caerphilly with a recorded capacity of 4.1 MW, and has been generating since 2017-03-30.

4.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-30
Solar Photovoltaics
Technology
Pearmat Solar
Caerphilly
Authority
Wales

Planning and build timeline

Application submitted2015-06-30
Permission granted2015-11-05
4 months after submission
Operational2017-03-30
17 months after consent

Caerphilly’s record on solar

Caerphilly has decided 7 solar farms and approved 100%, taking a median of 3.5 months. See every solar farm decision in Caerphilly

Other built sites within 15 km

SiteMWDistance
Land at Darran Farm
Solar Photovoltaics · Operational
2.61.7 km
Oakdale Business Park
Wind Onshore · Operational
41.9 km
Hafod-Y-Dafal Farm
Solar Photovoltaics · Operational
142.9 km
Upper Pant-Ysgawen Farm/Crumlin
Solar Photovoltaics · Operational
4.94 km
Silent Valley Landfill Scheme
Landfill Gas · Operational
2.75.8 km
Hendai Farm
Solar Photovoltaics · Operational
13.47.5 km
Gelliargwellt Uchaf Farm AD
Anaerobic Digestion · Operational
1.47.6 km
Cwmcaesingrug Farm
Solar Photovoltaics · Operational
107.7 km

How big is Manmoel Road Solar Park?

Manmoel Road Solar Park has a recorded installed capacity of 4.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Manmoel Road Solar Park?

REPD records the operator as Pearmat Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Manmoel Road Solar Park approved and built?

The application was submitted on 2015-06-30. Permission was granted on 2015-11-05, 4 months later. The site became operational on 2017-03-30, 17 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5437.