Renewable sitesHendai Farm

Hendai Farm

Hendai Farm is operational in Caerphilly with a recorded capacity of 13.4 MW, and has been generating since 2015-03-01.

13.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-01
Solar Photovoltaics
Technology
Conergy UK
Caerphilly
Authority
Wales

Planning and build timeline

Application submitted2013-12-10
Permission granted2014-04-10
4 months after submission
Operational2015-03-01
11 months after consent

Caerphilly’s record on solar

Caerphilly has decided 7 solar farms and approved 100%, taking a median of 3.5 months. See every solar farm decision in Caerphilly

Other built sites within 15 km

SiteMWDistance
Gelliargwellt Uchaf Farm AD
Anaerobic Digestion · Operational
1.41.2 km
Land at Darran Farm
Solar Photovoltaics · Operational
2.66.8 km
Pen Rhiw Caradog
Solar Photovoltaics · Operational
4.77.2 km
Oakdale Business Park
Wind Onshore · Operational
47.4 km
Manmoel Road Solar Park
Solar Photovoltaics · Operational
4.17.5 km
Trecatti
Landfill Gas · Operational
77.6 km
Land At Cwm Bargoed
Solar Photovoltaics · Operational
58.5 km
Cwmcaesingrug Farm
Solar Photovoltaics · Operational
108.6 km

How big is Hendai Farm?

Hendai Farm has a recorded installed capacity of 13.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hendai Farm?

REPD records the operator as Conergy UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hendai Farm approved and built?

The application was submitted on 2013-12-10. Permission was granted on 2014-04-10, 4 months later. The site became operational on 2015-03-01, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2370.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council