Renewable sites › Nevendon Battery Storage Extension
Nevendon Battery Storage Extension
Nevendon Battery Storage Extension is operational in Basildon with a recorded capacity of 5 MW, and has been generating since 2024-10-23.
Planning and build timeline
| Application submitted | 2023-01-26 |
| Permission granted | 2023-05-15 4 months after submission |
| Operational | 2024-10-23 17 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Basildon
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Basildon’s record on battery storage
Basildon has decided 6 battery storage schemes and approved 83%, taking a median of 7.9 months. See every battery storage scheme decision in Basildon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Nevendon Battery · Operational | 10 | 0 km |
Crays Hall Farm - Solar Arrays Solar Photovoltaics · Under Construction | 25.6 | 2.6 km |
Tesco Extra Hazelmere Solar Photovoltaics · Operational | 0.4 | 3.4 km |
Outwood Farm (Phase 1) Solar Photovoltaics · Operational | 5 | 4.6 km |
Dollymans Storage Battery · Operational | 99.98 | 4.8 km |
Pitsea Tipp Landfill Gas · Operational | 14 | 6.3 km |
Ford Research And Engineering Centre, Dunton - Solar Farm Solar Photovoltaics · Operational | 5.2 | 6.4 km |
Pitsea Landfill Scheme Landfill Gas · Operational | 11.6 | 6.4 km |
How big is Nevendon Battery Storage Extension?
Nevendon Battery Storage Extension has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Nevendon Battery Storage Extension?
REPD records the operator as Belectric Solar Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Nevendon Battery Storage Extension approved and built?
The application was submitted on 2023-01-26. Permission was granted on 2023-05-15, 4 months later. The site became operational on 2024-10-23, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 13197.