Renewable sites › Outwood Farm (Phase 1)
Outwood Farm (Phase 1)
Outwood Farm (Phase 1) is operational in Basildon with a recorded capacity of 5 MW, and has been generating since 2016-03-30.
Planning and build timeline
| Application submitted | 2014-08-07 |
| Permission granted | 2014-12-11 4 months after submission |
| Operational | 2016-03-30 16 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Basildon
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Basildon’s record on solar
Basildon has decided 12 solar farms and approved 100%, taking a median of 3.7 months. See every solar farm decision in Basildon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Crays Hall Farm - Solar Arrays Solar Photovoltaics · Under Construction | 25.6 | 2 km |
Nevendon Battery Storage Extension Battery · Operational | 5 | 4.6 km |
Nevendon Battery · Operational | 10 | 4.6 km |
Ford Research And Engineering Centre, Dunton - Solar Farm Solar Photovoltaics · Operational | 5.2 | 5.3 km |
Crouch Solar Farm Battery · Operational | 49.9 | 6 km |
Crouch Solar Farm Solar Photovoltaics · Operational | 49.9 | 6 km |
Hutton Battery Storage (Lower Road) Battery · Operational | 10 | 6.4 km |
Lower Dunton Road Battery Storage Facility Battery · Operational | 28 | 7.3 km |
How big is Outwood Farm (Phase 1)?
Outwood Farm (Phase 1) has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Outwood Farm (Phase 1)?
REPD records the operator as MS Power Projects. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Outwood Farm (Phase 1) approved and built?
The application was submitted on 2014-08-07. Permission was granted on 2014-12-11, 4 months later. The site became operational on 2016-03-30, 16 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2240.