Dollymans Storage is an operational 99.98 MW battery storage site in Basildon, generating since 1 July 2023. Planning permission was granted on 5 November 2021, 5 months after submission. Operator of record: Statera Energy / Dollymans Storage.

99.98 MW
Capacity
as recorded in REPD
Operational
Status
since 1 July 2023
Battery
Technology
Statera Energy / Dollymans Storage
Basildon
Authority
England

Planning and build timeline

Application submitted24 May 2021
Permission granted5 November 2021
5 months after submission
Operational1 July 2023
20 months after consent

Screening a site of your own?

RedlineUK · £39

Basildon approves 83% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Dollymans Storage’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Basildon’s record on battery storage

Basildon has decided 6 battery storage schemes and approved 83%, taking a median of 7.9 months. See every battery storage scheme decision in Basildon

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
302.7 km
Battery · Operational
104.8 km
Battery · Operational
54.8 km
Solar Photovoltaics · Operational
0.45.5 km
Solar Photovoltaics · Under Construction
25.66.9 km
Landfill Gas · Operational
11.67.3 km
Landfill Gas · Operational
147.4 km
Solar Photovoltaics · Operational
58.7 km

How big is Dollymans Storage?

Dollymans Storage has a recorded installed capacity of 99.98 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dollymans Storage?

REPD records the operator as Statera Energy / Dollymans Storage. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dollymans Storage approved and built?

The application was submitted on 24 May 2021. Permission was granted on 5 November 2021, 5 months later. The site became operational on 1 July 2023, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7088.