Nether Moor Field

Nether Moor Field is an operational 49.9 MW battery storage site in Rotherham, generating since 1 September 2020. Planning permission was granted on 21 December 2017, 3 months after submission. Operator of record: Thurcroft Energy (Max Design Consultancy).

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 September 2020
Battery
Technology
Thurcroft Energy (Max Design Consultancy)
Rotherham
Authority
England

Planning and build timeline

Application submitted29 September 2017
Permission granted21 December 2017
3 months after submission
Operational1 September 2020
32 months after consent

Screening a site of your own?

RedlineUK · £39

Rotherham approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Nether Moor Field’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Rotherham’s record on battery storage

Rotherham has decided 14 battery storage schemes and approved 100%, taking a median of 3.2 months. See every battery storage scheme decision in Rotherham

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
19.82.8 km
Battery · Operational
0.37.2 km
Biomass (dedicated) · Operational
427.4 km
Wind Onshore · Operational
2.67.4 km
Battery · Operational
108.9 km
Biomass (dedicated) · Operational
308.9 km
Biomass (dedicated) · Operational
6.58.9 km
Landfill Gas · Operational
1.19.6 km

How big is Nether Moor Field?

Nether Moor Field has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Nether Moor Field?

REPD records the operator as Thurcroft Energy (Max Design Consultancy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Nether Moor Field approved and built?

The application was submitted on 29 September 2017. Permission was granted on 21 December 2017, 3 months later. The site became operational on 1 September 2020, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7019.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode