Novarly ParcelRenewable sites

Renewable sitesNether Moor Field

Nether Moor Field

Nether Moor Field is operational in Rotherham with a recorded capacity of 49.9 MW, and has been generating since 2020-09-01.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2020-09-01
Battery
Technology
Thurcroft Energy (Max Design Consultancy)
Rotherham
Authority
England

Planning and build timeline

Application submitted2017-09-29
Permission granted2017-12-21
3 months after submission
Operational2020-09-01
32 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Rotherham’s record on battery storage

Rotherham has decided 14 battery storage schemes and approved 100%, taking a median of 3.2 months. See every battery storage scheme decision in Rotherham

Other built sites within 15 km

SiteMWDistance
Penny Hill Lane
Wind Onshore · Operational
19.82.8 km
Thrybergh Hydroelectric Scheme
Battery · Operational
0.37.2 km
Templeborough Biomass Power Plant- Rotherham
Biomass (dedicated) · Operational
427.4 km
Advanced Manufacturing Research Centre
Wind Onshore · Operational
2.67.4 km
Blackburn Meadows Biomass Plant
Biomass (dedicated) · Operational
308.9 km
Blackburn Meadows
Battery · Operational
108.9 km
Holbrook Community Renewable Energy Centre
Biomass (dedicated) · Operational
6.58.9 km
Meadow Hall Power
Landfill Gas · Operational
1.19.6 km

How big is Nether Moor Field?

Nether Moor Field has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Nether Moor Field?

REPD records the operator as Thurcroft Energy (Max Design Consultancy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Nether Moor Field approved and built?

The application was submitted on 2017-09-29. Permission was granted on 2017-12-21, 3 months later. The site became operational on 2020-09-01, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7019.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council