Penny Hill Lane

Penny Hill Lane is operational in Rotherham with a recorded capacity of 19.8 MW, and has been generating since 2013-03-31.

19.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-03-31
Wind Onshore
Technology
Banks Renewables
Rotherham
Authority
England

Planning and build timeline

Application submitted2009-07-22
Permission granted2010-05-27
10 months after submission
Operational2013-03-31
34 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Nether Moor Field
Battery · Operational
49.92.8 km
Advanced Manufacturing Research Centre
Wind Onshore · Operational
2.65.4 km
Holbrook Community Renewable Energy Centre
Biomass (dedicated) · Operational
6.56.3 km
Templeborough Biomass Power Plant- Rotherham
Biomass (dedicated) · Operational
426.7 km
Blackburn Meadows Biomass Plant
Biomass (dedicated) · Operational
307.9 km
Blackburn Meadows
Battery · Operational
107.9 km
Meadow Hall Power
Landfill Gas · Operational
1.18.7 km
Loscar Farm
Wind Onshore · Operational
4.58.7 km

How big is Penny Hill Lane?

Penny Hill Lane has a recorded installed capacity of 19.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Penny Hill Lane?

REPD records the operator as Banks Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Penny Hill Lane approved and built?

The application was submitted on 2009-07-22. Permission was granted on 2010-05-27, 10 months later. The site became operational on 2013-03-31, 34 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3677.