Novarly ParcelRenewable sites

Renewable sitesBlackburn Meadows Biomass Plant

Blackburn Meadows Biomass Plant

Blackburn Meadows Biomass Plant is an operational 30 MW biomass plant in Sheffield, generating since 7 July 2014. Planning permission was granted on 15 July 2008, 4 months after submission. Operator of record: E.ON UK.

30 MW
Capacity
as recorded in REPD
Operational
Status
since 7 July 2014
Biomass (dedicated)
Technology
E.ON UK
Sheffield
Authority
England

Planning and build timeline

Application submitted1 March 2008
Permission granted15 July 2008
4 months after submission
Operational7 July 2014
72 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Sheffield: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Blackburn Meadows Biomass Plant’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Battery · Operational
100 km
Landfill Gas · Operational
1.10.9 km
Biomass (dedicated) · Operational
421.7 km
Wind Onshore · Operational
2.63.9 km
Biomass (dedicated) · Operational
84.5 km
EfW Incineration · Operational
19.35 km
Landfill Gas · Operational
1.25.7 km
Wind Onshore · Operational
19.87.9 km

How big is Blackburn Meadows Biomass Plant?

Blackburn Meadows Biomass Plant has a recorded installed capacity of 30 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Blackburn Meadows Biomass Plant?

REPD records the operator as E.ON UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Blackburn Meadows Biomass Plant approved and built?

The application was submitted on 1 March 2008. Permission was granted on 15 July 2008, 4 months later. The site became operational on 7 July 2014, 72 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 166.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode