Planning and build timeline
| Application submitted | 2012-03-29 |
| Permission granted | 2012-09-25 6 months after submission |
| Operational | 2017-04-24 55 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
The Breck Solar Photovoltaics · Operational | 5 | 5.9 km |
Penny Hill Lane Wind Onshore · Operational | 19.8 | 6.3 km |
Staveley Power Landfill Gas · Operational | 2.1 | 6.6 km |
Loscar Farm Wind Onshore · Operational | 4.5 | 6.7 km |
Advanced Manufacturing Research Centre Wind Onshore · Operational | 2.6 | 7 km |
Land at Oxcroft Stocking Ground Solar Photovoltaics · Operational | 4 | 7.7 km |
Inkersall Road, Staveley - Solar Photovoltaic Farm And Battery Storage Solar Photovoltaics · Operational | 31 | 8.1 km |
Inkersall Road, Staveley - Solar Photovoltaic Farm And Battery Storage Battery · Operational | — | 8.1 km |
How big is Holbrook Community Renewable Energy Centre?
Holbrook Community Renewable Energy Centre has a recorded installed capacity of 6.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Holbrook Community Renewable Energy Centre?
REPD records the operator as UYE (UK) / Veolia. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Holbrook Community Renewable Energy Centre approved and built?
The application was submitted on 2012-03-29. Permission was granted on 2012-09-25, 6 months later. The site became operational on 2017-04-24, 55 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 117.