Blackburn Meadows is operational in Sheffield with a recorded capacity of 10 MW, and has been generating since 2017-10-09.

10 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-10-09
Battery
Technology
E.ON UK
Sheffield
Authority
England

Planning and build timeline

Application submitted2011-08-19
Permission grantednot recorded
Operational2017-10-09

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Sheffield’s record on battery storage

Sheffield has decided 7 battery storage schemes and approved 100%, taking a median of 5.9 months. See every battery storage scheme decision in Sheffield

Other built sites within 15 km

SiteMWDistance
Blackburn Meadows Biomass Plant
Biomass (dedicated) · Operational
300 km
Meadow Hall Power
Landfill Gas · Operational
1.10.9 km
Templeborough Biomass Power Plant- Rotherham
Biomass (dedicated) · Operational
421.7 km
Advanced Manufacturing Research Centre
Wind Onshore · Operational
2.63.9 km
Loicher Lane
Biomass (dedicated) · Operational
84.5 km
Sheffield ERF
EfW Incineration · Operational
19.35 km
Parkwood Landfill Scheme
Landfill Gas · Operational
1.25.7 km
Penny Hill Lane
Wind Onshore · Operational
19.87.9 km

How big is Blackburn Meadows?

Blackburn Meadows has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Blackburn Meadows?

REPD records the operator as E.ON UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Blackburn Meadows approved and built?

The application was submitted on 2011-08-19. REPD does not record a grant date. The site became operational on 2017-10-09.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6906.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council