Native River

Native River is an operational 57 MW battery storage site in Cheshire West and Chester, generating since 14 April 2025. Planning permission was granted on 16 April 2021, 4 months after submission. Operator of record: Varco Energy.

57 MW
Capacity
as recorded in REPD
Operational
Status
since 14 April 2025
Battery
Technology
Varco Energy
Cheshire West and Chester
Authority
England

Planning and build timeline

Application submitted17 December 2020
Permission granted16 April 2021
4 months after submission
Operational14 April 2025
48 months after consent

Screening a site of your own?

RedlineUK · £39

Cheshire West and Chester approves 91% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Native River’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cheshire West and Chester’s record on battery storage

Cheshire West and Chester has decided 11 battery storage schemes and approved 91%, taking a median of 9.2 months. See every battery storage scheme decision in Cheshire West and Chester

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
570.4 km
Battery · Operational
1001 km
Solar Photovoltaics · Operational
0.224.1 km
Advanced Conversion Technologies · Under Construction
285 km
Solar Photovoltaics · Operational
72.25.8 km
Solar Photovoltaics · Operational
1.26.4 km
EfW Incineration · Operational
166.7 km
Solar Photovoltaics · Operational
3.86.7 km

How big is Native River?

Native River has a recorded installed capacity of 57 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Native River?

REPD records the operator as Varco Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Native River approved and built?

The application was submitted on 17 December 2020. Permission was granted on 16 April 2021, 4 months later. The site became operational on 14 April 2025, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8283.