Hooton Park is a 28 MW advanced conversion plant under construction in Wirral. Planning permission was granted on 29 July 2009, 12 months after submission. Operator of record: Cogen.
Planning and build timeline
| Application submitted | 15 July 2008 |
| Permission granted | 29 July 2009 12 months after submission |
| Operational | not recorded |
Screening a site of your own?
Redline runs the record on your own boundary in Wirral: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Hooton Park’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Under Construction | 57 | 4.7 km |
Battery · Operational | 57 | 5 km |
Landfill Gas · Operational | 3.7 | 5.2 km |
Landfill Gas · Operational | 3 | 5.9 km |
Battery · Operational | 100 | 6 km |
Solar Photovoltaics · Operational | 0.22 | 6.5 km |
Solar Photovoltaics · Operational | 1.2 | 6.8 km |
EfW Incineration · Under Construction | 35 | 7.9 km |
How big is Hooton Park?
Hooton Park has a recorded installed capacity of 28 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hooton Park?
REPD records the operator as Cogen. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hooton Park approved and built?
The application was submitted on 15 July 2008. Permission was granted on 29 July 2009, 12 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1002.