Renewable sites › Hooton Park
Hooton Park
Hooton Park is under construction in Wirral with a recorded capacity of 28 MW.
Planning and build timeline
| Application submitted | 2008-07-15 |
| Permission granted | 2009-07-29 12 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Capenhurst Lane, Capenhurst - Battery storage Battery · Under Construction | 57 | 4.7 km |
Native River Battery · Operational | 57 | 5 km |
Bromborough Dock Landfill Gas · Operational | 3.7 | 5.2 km |
Bromborough Dock Landfill Scheme Landfill Gas · Operational | 3 | 5.9 km |
National Grid Electricity Substation, Capenhurst Lane - Battery Storage Battery · Operational | 100 | 6 km |
Longlooms Road East - Solar panels Solar Photovoltaics · Operational | 0.22 | 6.5 km |
Aldi Distribution Centre - Neston Solar Photovoltaics · Operational | 1.2 | 6.8 km |
Plot 8 Protos/Ince Marshes EfW Incineration · Under Construction | 35 | 7.9 km |
How big is Hooton Park?
Hooton Park has a recorded installed capacity of 28 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hooton Park?
REPD records the operator as Cogen. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hooton Park approved and built?
The application was submitted on 2008-07-15. Permission was granted on 2009-07-29, 12 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1002.
Novarly Parcel · official public data, read properly · parcel.novarly.com