Novarly ParcelRenewable sites

Renewable sitesHooton Park

Hooton Park

Hooton Park is a 28 MW advanced conversion plant under construction in Wirral. Planning permission was granted on 29 July 2009, 12 months after submission. Operator of record: Cogen.

28 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Advanced Conversion Technologies
Technology
Cogen
Wirral
Authority
England

Planning and build timeline

Application submitted15 July 2008
Permission granted29 July 2009
12 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Wirral: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hooton Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
574.7 km
Battery · Operational
575 km
Landfill Gas · Operational
3.75.2 km
Landfill Gas · Operational
35.9 km
Battery · Operational
1006 km
Solar Photovoltaics · Operational
0.226.5 km
Solar Photovoltaics · Operational
1.26.8 km
EfW Incineration · Under Construction
357.9 km

How big is Hooton Park?

Hooton Park has a recorded installed capacity of 28 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hooton Park?

REPD records the operator as Cogen. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hooton Park approved and built?

The application was submitted on 15 July 2008. Permission was granted on 29 July 2009, 12 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1002.