Renewable sites › Mill Farm
Mill Farm
Mill Farm is operational in East Hertfordshire with a recorded capacity of 5 MW, and has been generating since 2016-12-15.
Planning and build timeline
| Application submitted | 2015-11-09 |
| Permission granted | 2016-07-20 8 months after submission |
| Operational | 2016-12-15 5 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Hertfordshire’s record on solar
East Hertfordshire has decided 10 solar farms and approved 90%, taking a median of 1.8 months. See every solar farm decision in East Hertfordshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Buttermilk Farm Anaerobic Digestion · Operational | 1.1 | 4.4 km |
Westmill Qaurry Landfill Gas · Operational | 2.6 | 9.5 km |
Brazier Landfill Scheme Landfill Gas · Operational | 3.9 | 10.2 km |
Wisbridge Farm Solar Photovoltaics · Operational | 9.3 | 11.4 km |
Flamingo House Solar Photovoltaics · Operational | 1 | 11.6 km |
The Nurseries, Green Tye Anaerobic Digestion · Operational | 1.2 | 11.7 km |
Pelham Battery · Operational | 49 | 11.9 km |
Bygrave Lodge Farm Anaerobic Digestion Facility (Farm AD) Anaerobic Digestion · Operational | 2.3 | 12.5 km |
How big is Mill Farm?
Mill Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Mill Farm?
REPD records the operator as Push Energy/ NextEnergy Solar Fund (NESF). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Mill Farm approved and built?
The application was submitted on 2015-11-09. Permission was granted on 2016-07-20, 8 months later. The site became operational on 2016-12-15, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5887.