Wisbridge Farm is operational in North Hertfordshire with a recorded capacity of 9.3 MW, and has been generating since 2014-10-01.
Planning and build timeline
| Application submitted | 2012-10-23 |
| Permission granted | 2013-03-27 5 months after submission |
| Operational | 2014-10-01 18 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Conservation area — Reed
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Hertfordshire’s record on solar
North Hertfordshire has decided 8 solar farms and approved 88%, taking a median of 20.3 months. See every solar farm decision in North Hertfordshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Hatch Penn Farm PV Solar Photovoltaics · Operational | 1 | 1.5 km |
Royston Solar Farm (Phase 1) (a) Solar Photovoltaics · Operational | 5 | 6.4 km |
Munceys Farm Solar Photovoltaics · Operational | 31.6 | 6.5 km |
Bassingbourn Solar Farm Solar Photovoltaics · Operational | 14.4 | 7.2 km |
Buttermilk Farm Anaerobic Digestion · Operational | 1.1 | 7.2 km |
Bury Lane Fruit Farm Solar Photovoltaics · Operational | 24 | 8 km |
Bygrave Lodge Farm Anaerobic Digestion Facility (Farm AD) Anaerobic Digestion · Operational | 2.3 | 8.9 km |
Black Peak Farm Solar Photovoltaics · Operational | 31.8 | 8.9 km |
How big is Wisbridge Farm?
Wisbridge Farm has a recorded installed capacity of 9.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wisbridge Farm?
REPD records the operator as Push Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wisbridge Farm approved and built?
The application was submitted on 2012-10-23. Permission was granted on 2013-03-27, 5 months later. The site became operational on 2014-10-01, 18 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1940.