Renewable sites › Westmill Qaurry
Westmill Qaurry
Westmill Qaurry is operational in East Hertfordshire with a recorded capacity of 2.6 MW, and has been generating since 2000-06-01.
Planning and build timeline
| Application submitted | 1999-03-18 |
| Permission granted | 1999-07-19 4 months after submission |
| Operational | 2000-06-01 10 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
- Green Belt — East Hertfordshire
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Brazier Landfill Scheme Landfill Gas · Operational | 3.9 | 0.7 km |
Ratty's Lane Sustainable Energy Facility (Waste AD) Anaerobic Digestion · Operational | 3 | 7.3 km |
Ratty's Lane Sustainable Energy Facility (ACT) Advanced Conversion Technologies · Under Construction | 9.6 | 7.3 km |
Rye Meads Sewerage Treatment Works Anaerobic Digestion · Operational | 2.3 | 7.4 km |
Mill Farm Solar Photovoltaics · Operational | 5 | 9.5 km |
The Nurseries, Green Tye Anaerobic Digestion · Operational | 1.2 | 10.6 km |
Buttermilk Farm Anaerobic Digestion · Operational | 1.1 | 13.9 km |
Computacenter Warehouse Solar Photovoltaics · Under Construction | 2 | 14.1 km |
How big is Westmill Qaurry?
Westmill Qaurry has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Westmill Qaurry?
REPD records the operator as Hertfordshire County Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Westmill Qaurry approved and built?
The application was submitted on 1999-03-18. Permission was granted on 1999-07-19, 4 months later. The site became operational on 2000-06-01, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 631.