Renewable sites › Flamingo House
Flamingo House
Flamingo House is operational in Stevenage with a recorded capacity of 1 MW, and has been generating since 2020-12-01.
Planning and build timeline
| Application submitted | 2019-04-08 |
| Permission granted | 2019-10-07 6 months after submission |
| Operational | 2020-12-01 14 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Stevenage’s record on solar
Stevenage has decided 7 solar farms and approved 100%, taking a median of 1.5 months. See every solar farm decision in Stevenage →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Hitchin Landfill Gas · Operational | 1.5 | 9.8 km |
Ld At Lawrence End Park &, Dane Street Solar Photovoltaics · Operational | 5 | 10.4 km |
Land North of Chiltern Greeen Solar Photovoltaics · Operational | 5 | 10.6 km |
Arlesey Landfill Gas (Extension) Landfill Gas · Operational | 2.3 | 11.5 km |
Arlesey Landfill Site Landfill Gas · Operational | 1.1 | 11.5 km |
Mill Farm Solar Photovoltaics · Operational | 5 | 11.6 km |
Bygrave Lodge Farm Anaerobic Digestion Facility (Farm AD) Anaerobic Digestion · Operational | 2.3 | 11.9 km |
Buttermilk Farm Anaerobic Digestion · Operational | 1.1 | 12.4 km |
How big is Flamingo House?
Flamingo House has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Flamingo House?
REPD records the operator as M & G. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Flamingo House approved and built?
The application was submitted on 2019-04-08. Permission was granted on 2019-10-07, 6 months later. The site became operational on 2020-12-01, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7374.
Novarly Parcel · official public data, read properly · parcel.novarly.com