Novarly ParcelRenewable sites

Renewable sitesFlamingo House

Flamingo House

Flamingo House is an operational 1 MW solar farm in Stevenage, generating since 1 December 2020. Planning permission was granted on 7 October 2019, 6 months after submission. Operator of record: M & G.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 1 December 2020
Solar Photovoltaics
Technology
M & G
Stevenage
Authority
England

Planning and build timeline

Application submitted8 April 2019
Permission granted7 October 2019
6 months after submission
Operational1 December 2020
14 months after consent

Screening a site of your own?

RedlineUK · £39

Stevenage approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Flamingo House’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Stevenage’s record on solar

Stevenage has decided 7 solar farms and approved 100%, taking a median of 1.5 months. See every solar farm decision in Stevenage

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
1.59.8 km
Solar Photovoltaics · Operational
510.4 km
Solar Photovoltaics · Operational
510.6 km
Landfill Gas · Operational
2.311.5 km
Landfill Gas · Operational
1.111.5 km
Solar Photovoltaics · Operational
511.6 km
Anaerobic Digestion · Operational
2.311.9 km
Anaerobic Digestion · Operational
1.112.4 km

How big is Flamingo House?

Flamingo House has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Flamingo House?

REPD records the operator as M & G. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Flamingo House approved and built?

The application was submitted on 8 April 2019. Permission was granted on 7 October 2019, 6 months later. The site became operational on 1 December 2020, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7374.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode