Renewable sites › Bygrave Lodge Farm Anaerobic Digestion Facility (Farm AD)
Bygrave Lodge Farm Anaerobic Digestion Facility (Farm AD)
Bygrave Lodge Farm Anaerobic Digestion Facility (Farm AD) is operational in North Hertfordshire with a recorded capacity of 2.3 MW, and has been generating since 2014-09-20.
Planning and build timeline
| Application submitted | 2011-02-03 |
| Permission granted | 2013-05-01 27 months after submission |
| Operational | 2014-09-20 17 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — North Hertfordshire
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Langford Solar Farm Solar Photovoltaics · Operational | 13 | 8.7 km |
Arlesey Landfill Gas (Extension) Landfill Gas · Operational | 2.3 | 8.8 km |
Wisbridge Farm Solar Photovoltaics · Operational | 9.3 | 8.9 km |
Buttermilk Farm Anaerobic Digestion · Operational | 1.1 | 9 km |
Hatch Penn Farm PV Solar Photovoltaics · Operational | 1 | 9.1 km |
Arlesey Landfill Site Landfill Gas · Operational | 1.1 | 9.2 km |
Langford Wind Farm Wind Onshore · Operational | 20 | 9.4 km |
Bassingbourn Solar Farm Solar Photovoltaics · Operational | 14.4 | 10.2 km |
How big is Bygrave Lodge Farm Anaerobic Digestion Facility (Farm AD)?
Bygrave Lodge Farm Anaerobic Digestion Facility (Farm AD) has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bygrave Lodge Farm Anaerobic Digestion Facility (Farm AD)?
REPD records the operator as Ancala Bioenergy (formerly Biogen). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bygrave Lodge Farm Anaerobic Digestion Facility (Farm AD) approved and built?
The application was submitted on 2011-02-03. Permission was granted on 2013-05-01, 27 months later. The site became operational on 2014-09-20, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 271.
Novarly Parcel · official public data, read properly · parcel.novarly.com