Solar planning in East Hertfordshire

East Hertfordshire has decided 10 solar farms and approved 90% of them, taking a median of 1.8 months to decide. Consented capacity: 65 MW. 7 applications still awaiting a decision.

90%
Approved
9 granted · 1 refused
1.8 mo
Median decision
UK 2.3 mo
65 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How East Hertfordshire compares

Against the 298 UK authorities with 5+ solar decisions, East Hertfordshire sits in the 25th percentile for approval rate (3 points below the England average) and the 74th percentile for speed.

Decisions by year

35Approved — 1 (2016)116Approved — 1 (2022)122Approved — 3 (2023)Refused — 1 (2023)423Approved — 3 (2024)324Approved — 1 (2025)125
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (19)

SchemeMWStatusDecided
Ware Solar Park - Solar Farm & Battery Energy Storage
The Farm Energy Company · 3/24/1275/FUL · 15.2 mo to decide
24Awaiting Construction2025-10-17
Great Notley Field, Bromley Lane - Solar Array
Chaldean Properties Limited · 3/25/1111/FUL
0.28Application Submitted2025-09-09
Beane Solar Farm - Solar Panels
Renewable Energy Systems RES ltd (Beaufort) · 3/24/2245/FUL
49.9Application Submitted2024-12-20
Herts And Essex High School, Warwick Road - Solar Panels
Solar Options for Schools Limited · 3/24/1956/PNPV · 1.1 mo to decide
0.35Awaiting Construction2024-11-25
Herts and Essex Sports Centre, Beldams Lane - Solar Panels
Solar Options for Schools Limited · 3/24/1838/PNPV · 1.6 mo to decide
0.23Awaiting Construction2024-11-18
Major Barclay Farms, Beeches Manor - Solar PV Panels
Nathan Upshall · 3/24/1804/PNPV
0.2Application Withdrawn2024-10-30
Herts And Essex High School, Warwick Road - Solar Panels
Solar Options for Schools Limited · 3/24/1576/PNPV · 1.6 mo to decide
0.27Revised2024-10-15
Hertford Industrial Estate, Caxton Hill - Solar Panels
Marbank Construction Limited · 3/24/1192/PNPV
0.37Application Withdrawn2024-08-08
Hockerill Anglo European College, Dunmow Road - Solar panels
Solar Options for Schools Limited · 3/23/2379/FUL · 5.3 mo to decide
0.29Awaiting Construction2024-06-14
Hockerill Anglo European College, Dunmow Road - Solar panels
Solar Options for Schools Limited · 3/23/2379/FUL
0.29Application Submitted2024-01-05
Wickham Hall Estate Solar Photovoltaic Farm
Endurance Energy Wickham Hall Limited · 3/21/2601/FUL · 24.6 mo to decide
35Awaiting Construction2023-12-19
Westmill Quarry, Westmill Road - Solar Farm
Biffa Waste Services Limited · PL/0357/23
7.3Application Submitted2023-09-01
Haslemere Industrial Estate, Pig Lane - Solar Panels
Stagecoach Group Plc · 3/23/1062/PNPV · 1.6 mo to decide
0.3Application Refused2023-07-19
Stephen Austin & Sons, Caxton Hill - Solar Panels
Stephen Austin & Sons Limited · 3/23/0808/PNPV · 4.2 mo to decide
0.27Awaiting Construction2023-06-16
Stephen Austin & Sons, Caxton Hill - Solar System
Stephen Austin Limited · 3/23/0211/PNPV · 1.6 mo to decide
0.27Revised2023-03-24
Mercedes Benz Of Hertford, Foxholes Business Park - Solar Panels
Mercedes-Benz of Hertford · 3/23/0189/PNPV · 1.6 mo to decide
0.15Awaiting Construction2023-03-23
County Hall - Solar panels
Hertfordshire County Council · PL/0255/22 · 1.8 mo to decide
0.2Awaiting Construction2022-04-07
Mill Farm
Push Energy/ NextEnergy Solar Fund (NESF) · 3/15/2254/FUL · 8.3 mo to decide
5Operational2016-07-20
Mill Farm
Push Energy · 3/14/1058/FP · 4.9 mo to decide
9.6Revised2014-11-12

Does East Hertfordshire approve solar farms?

Yes — of the 10 solar farms East Hertfordshire has decided, 90% were approved (9 granted, 1 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in East Hertfordshire?

The median time from application to decision is 1.8 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has East Hertfordshire consented?

65 MW has been consented across 9 approved schemes. A further 7 applications awaits a decision.

Other technologies in East Hertfordshire

Battery storage in East HertfordshireOnshore wind in East Hertfordshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.