Renewable sitesLynemouth Windfarm (Resubmission)

Lynemouth Windfarm (Resubmission)

Lynemouth Windfarm (Resubmission) is an operational 26 MW onshore wind farm in Northumberland, generating since 12 April 2012. Planning permission was granted on 8 January 2009, 26 months after submission. Operator of record: Scottish Power Renewables.

26 MW
Capacity
as recorded in REPD
Operational
Status
since 12 April 2012
Wind Onshore
Technology
Scottish Power Renewables
Northumberland
Authority
England

Planning and build timeline

Application submitted20 November 2006
Permission granted8 January 2009
26 months after submission
Operational12 April 2012
39 months after consent

Screening a site of your own?

RedlineUK · £39

Northumberland approves 52% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Lynemouth Windfarm (Resubmission)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Northumberland’s record on onshore wind

Northumberland has decided 31 onshore wind schemes and approved 52%, taking a median of 16.3 months. See every onshore wind scheme decision in Northumberland

Other built sites within 15 km

SiteMWDistance
Biomass (dedicated) · Operational
4200.7 km
Wind Onshore · Operational
2.31.9 km
Anaerobic Digestion · Operational
0.56.1 km
Wind Onshore · Operational
8.27.3 km
Solar Photovoltaics · Operational
2.37.7 km
Wind Onshore · Operational
3.48.5 km
Wind Onshore · Operational
18.458.9 km
Wind Onshore · Operational
2.78.9 km

How big is Lynemouth Windfarm (Resubmission)?

Lynemouth Windfarm (Resubmission) has a recorded installed capacity of 26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lynemouth Windfarm (Resubmission)?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lynemouth Windfarm (Resubmission) approved and built?

The application was submitted on 20 November 2006. Permission was granted on 8 January 2009, 26 months later. The site became operational on 12 April 2012, 39 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3752.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode