Novarly ParcelRenewable sites

Renewable sitesNorth Steads Wind Farm

North Steads Wind Farm

North Steads Wind Farm is an operational 18.45 MW onshore wind farm in Northumberland, generating since 4 July 2016. Planning permission was granted on 6 November 2012, 9 months after submission. Operator of record: Ventient (formerly Infinis).

18.45 MW
Capacity
as recorded in REPD
Operational
Status
since 4 July 2016
Wind Onshore
Technology
Ventient (formerly Infinis)
Northumberland
Authority
England

Planning and build timeline

Application submitted30 January 2012
Permission granted6 November 2012
9 months after submission
Operational4 July 2016
44 months after consent

Screening a site of your own?

RedlineUK · £39

Northumberland approves 52% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with North Steads Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Northumberland’s record on onshore wind

Northumberland has decided 31 onshore wind schemes and approved 52%, taking a median of 16.3 months. See every onshore wind scheme decision in Northumberland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
8.21.7 km
Wind Onshore · Operational
2.37 km
Anaerobic Digestion · Operational
0.58.2 km
Biomass (dedicated) · Operational
4208.8 km
Wind Onshore · Operational
268.9 km
Wind Onshore · Operational
1511 km
Battery · Operational
0.413 km
Solar Photovoltaics · Operational
0.813 km

How big is North Steads Wind Farm?

North Steads Wind Farm has a recorded installed capacity of 18.45 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates North Steads Wind Farm?

REPD records the operator as Ventient (formerly Infinis). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was North Steads Wind Farm approved and built?

The application was submitted on 30 January 2012. Permission was granted on 6 November 2012, 9 months later. The site became operational on 4 July 2016, 44 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3905.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode