Novarly ParcelRenewable sites

Renewable sitesLynemouth Power Station

Lynemouth Power Station

Lynemouth Power Station is an operational 420 MW biomass plant in Northumberland, generating since 21 November 2018. Planning permission was granted on 6 March 2015, 2 months after submission. Operator of record: Lynemouth Power.

420 MW
Capacity
as recorded in REPD
Operational
Status
since 21 November 2018
Biomass (dedicated)
Technology
Lynemouth Power
Northumberland
Authority
England

Planning and build timeline

Application submitted12 January 2015
Permission granted6 March 2015
2 months after submission
Operational21 November 2018
45 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Northumberland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Lynemouth Power Station’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
260.7 km
Wind Onshore · Operational
2.31.8 km
Anaerobic Digestion · Operational
0.56.7 km
Wind Onshore · Operational
8.27.3 km
Solar Photovoltaics · Operational
2.38.2 km
Wind Onshore · Operational
18.458.8 km
Wind Onshore · Operational
3.48.9 km
Wind Onshore · Operational
2.79.4 km

How big is Lynemouth Power Station?

Lynemouth Power Station has a recorded installed capacity of 420 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lynemouth Power Station?

REPD records the operator as Lynemouth Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lynemouth Power Station approved and built?

The application was submitted on 12 January 2015. Permission was granted on 6 March 2015, 2 months later. The site became operational on 21 November 2018, 45 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 115.