Onshore wind planning in Northumberland

Northumberland has decided 31 onshore wind schemes and approved 52% of them, taking a median of 16.3 months to decide. Consented capacity: 273 MW. 3 applications still awaiting a decision.

52%
Approved
16 granted · 15 refused
16.3 mo
Median decision
UK 11.5 mo
273 MW
Consented
293 MW refused
13
Appeals
8 allowed on appeal

How Northumberland compares

Against the 75 UK authorities with 5+ onshore wind decisions, Northumberland sits in the 22nd percentile for approval rate (16 points below the England average) and the 31st percentile for speed.

Decisions by year

510Approved — 3 (2010)Refused — 3 (2010)610Approved — 1 (2011)111Approved — 1 (2012)Refused — 1 (2012)212Approved — 1 (2013)Refused — 1 (2013)213Refused — 3 (2014)314Refused — 1 (2015)115Approved — 1 (2024)124
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (38)

SchemeMWStatusDecided
East Sleekburn - Wind Farm
Berwick Bank Wind Farm Limited · 23/04110/OUT · 12.2 mo to decide
Awaiting Construction2024-11-06
Charlton Mires
Redpath Energy Limited · 14/01548/RENE · 15.4 mo to decide
1.5Application Refused2015-09-14
Land East of Mount Pleasant Farm
Still Wind · 15/00454/RENEIA
1.5Application Withdrawn2015-06-03
Belford Burn Windfarm
Energiekontor UK · 13/02050/RENEIA · 15 mo to decide
22.5Application Refused2014-10-08
Rayburn Wind Farm
Renewable Energy Systems (RES) · 13/03346/RENEIA · 10.9 mo to decide
10Application Refused2014-10-07
Tranwell Airfield Wind Farm
Wind Ventures · 12/03731/RENEIA · 13.6 mo to decide
8Application Refused2014-01-30
Sisters
Infinis (formerly Novera Energy) · 11/02481/RENEIA · 16.3 mo to decide
8.2Operational2013-02-06
Fenrother Wind Farm
Energiekontor UK · 12/02500/RENEIA · 5.3 mo to decide
15Appeal Refused2013-01-16
North Steads Wind Farm
Ventient (formerly Infinis) · 12/00290/RENEIA · 9.2 mo to decide
18.45Operational2012-11-06
Wingates Moor Wind Farm
BT · 11/00158/RENEIA · 12.2 mo to decide
6Application Refused2012-03-22
Rayburn Lake Wind Farm
Renewable Energy Systems (RES) · C/09/00154/RENEIA
18Application Withdrawn2011-11-01
Wingates Wind Farm
Ventient (formerly Infinis) · C/09/00084/CCMEIA · 28.9 mo to decide
15Operational2011-05-04
Ancroft Northmoor Wind Farm
E.ON UK · C/09/00063/CCMEIA
16Application Withdrawn2011-04-06
Ray Wind Farm
Vattenfall · 06/00023/CPC · 59 mo to decide
54.4Operational2010-11-11
Kirkharle Wind Farm
Npower Renewables · 20081063 · 22.4 mo to decide
20Application Refused2010-09-30
Todd Hill Wind Farm
Novera Energy · 09/00083/CCMEIA · 18 mo to decide
10Application Refused2010-06-01
Green Rigg
EDF/China General Nuclear Power Corporation · 20060040 · 50.4 mo to decide
36Operational2010-03-26
Steadings Wind Farm
Banks Group · 06/0075/CPC · 47.4 mo to decide
66Application Refused2010-03-25
Barmoor South Wind Farm
EDF · C/07/00180/CPC · 26 mo to decide
13.8Operational2010-01-21
Moneylaws Hill
ANGOLD ASSOCIATES
11.2Application Withdrawn2009-06-10
Lynemouth Windfarm (Resubmission)
Scottish Power Renewables · CM/20060984 · 25.6 mo to decide
26Operational2009-01-08
Kiln Pit Hill Windfarm
Npower Renewables · 20060052 · 34.6 mo to decide
12Operational2009-01-02
Middlemoor
Npower Renewables · ELEC/2005/0004 · 32 mo to decide
54Operational2008-08-07
MSD Cramlington
Unknown · 06-00551-FUL · 19.4 mo to decide
4Operational2008-07-24
Blyth Harbour Wind Farm (re-power)
Hainsford Energy · 07/00287/FULES · 12.5 mo to decide
3.4Operational2008-07-21
Moorsyde Wind Farm
Your Energy · 04/B/1107 · 38.4 mo to decide
16.1Appeal Refused2008-03-27
Barmoor
Force 9 Energy/Catamount · 06/B/0148 · 24.8 mo to decide
27Revised2008-03-27
Toft Hill Windfarm
Npower Renewables · 06/B/1001 · 16.4 mo to decide
19Appeal Refused2008-03-27
Lynemouth Windfarm
Scottish Power Renewables · CM/20060877 · 16.3 mo to decide
2.4Revised2008-02-20
Wandylaw
Blue Energy · 06/B/0765 · 18.3 mo to decide
20.5Operational2008-02-10
Bewick Drift
Harworth Power · CM/20060877 · 15.6 mo to decide
2.3Operational2008-02-01
Aesica Pharmaceuticals
Aesica Pharmaceuticals · B/06/00384/RES · 8.4 mo to decide
6Application Refused2007-02-01
Debdon Farm Wind Farm
Renewable Energy Systems (RES) · A/2006/0348 · 2.1 mo to decide
10.1Application Refused2006-09-05
Aesica Pharmaceuticals Limited
Aesica Pharmaceuticals Limited · 06/00275/FUL · 3.1 mo to decide
6Revised2006-08-25
Wandystead
G. Y. McNay Trust (a front for National Wind Power) · A/2002/0013 · 5.6 mo to decide
3.9Appeal Refused2002-06-26
Humble Hill Wind Farm
Ecogen · 108.6 mo to decide
78.5Appeal Refused2002-05-02
Kirkheaton Wind Farm
Border Wind Farms Ltd /AMEC · 14.6 mo to decide
1.8Operational1999-01-21
Blyth Harbour Wind Farm
Border Wind Farms Ltd · 91/00011/181OTH · 9.5 mo to decide
2.7Operational1992-03-06

Does Northumberland approve onshore wind schemes?

Yes — of the 31 onshore wind schemes Northumberland has decided, 52% were approved (16 granted, 15 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Northumberland?

The median time from application to decision is 16.3 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Northumberland consented?

273 MW has been consented across 16 approved schemes, with 293 MW refused. A further 3 applications awaits a decision.

Other technologies in Northumberland

Solar in NorthumberlandBattery storage in Northumberland

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.