Novarly ParcelRenewable sites

Renewable sitesBlyth Sewage Treatment Works

Blyth Sewage Treatment Works

Blyth Sewage Treatment Works is an operational 2.3 MW solar farm in Northumberland, generating since 14 September 2021. Planning permission was granted on 13 January 2021, 2 months after submission. Operator of record: Northumbrian Water Limited Head Office.

2.3 MW
Capacity
as recorded in REPD
Operational
Status
since 14 September 2021
Solar Photovoltaics
Technology
Northumbrian Water Limited Head Office
Northumberland
Authority
England

Planning and build timeline

Application submitted3 November 2020
Permission granted13 January 2021
2 months after submission
Operational14 September 2021
8 months after consent

Screening a site of your own?

RedlineUK · £39

Northumberland approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Blyth Sewage Treatment Works’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Northumberland’s record on solar

Northumberland has decided 31 solar farms and approved 100%, taking a median of 1.9 months. See every solar farm decision in Northumberland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
3.42.6 km
Wind Onshore · Operational
2.72.9 km
Wind Onshore · Operational
46.2 km
Biomass (dedicated) · Operational
27.76.6 km
Wind Onshore · Operational
267.7 km
Landfill Gas · Operational
4.17.8 km
Biomass (dedicated) · Operational
4208.2 km
Anaerobic Digestion · Operational
0.58.9 km

How big is Blyth Sewage Treatment Works?

Blyth Sewage Treatment Works has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Blyth Sewage Treatment Works?

REPD records the operator as Northumbrian Water Limited Head Office. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Blyth Sewage Treatment Works approved and built?

The application was submitted on 3 November 2020. Permission was granted on 13 January 2021, 2 months later. The site became operational on 14 September 2021, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8202.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode