Novarly ParcelRenewable sites

Renewable sitesBlyth Harbour Wind Farm

Blyth Harbour Wind Farm

Blyth Harbour Wind Farm is an operational 2.7 MW onshore wind farm in Northumberland, generating since 1 December 1992. Planning permission was granted on 6 March 1992, 9 months after submission. Operator of record: Border Wind Farms Ltd.

2.7 MW
Capacity
as recorded in REPD
Operational
Status
since 1 December 1992
Wind Onshore
Technology
Border Wind Farms Ltd
Northumberland
Authority
England

Planning and build timeline

Application submitted23 May 1991
Permission granted6 March 1992
9 months after submission
Operational1 December 1992
9 months after consent

Screening a site of your own?

RedlineUK · £39

Northumberland approves 52% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Blyth Harbour Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Northumberland’s record on onshore wind

Northumberland has decided 31 onshore wind schemes and approved 52%, taking a median of 16.3 months. See every onshore wind scheme decision in Northumberland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
3.40.5 km
Solar Photovoltaics · Operational
2.32.9 km
Landfill Gas · Operational
4.17.5 km
Wind Onshore · Operational
48.5 km
Biomass (dedicated) · Operational
27.78.6 km
Wind Onshore · Operational
268.9 km
Biomass (dedicated) · Operational
4209.4 km
Wind Offshore · Operational
41.59.5 km

How big is Blyth Harbour Wind Farm?

Blyth Harbour Wind Farm has a recorded installed capacity of 2.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Blyth Harbour Wind Farm?

REPD records the operator as Border Wind Farms Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Blyth Harbour Wind Farm approved and built?

The application was submitted on 23 May 1991. Permission was granted on 6 March 1992, 9 months later. The site became operational on 1 December 1992, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3659.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode