Blyth Harbour Wind Farm (re-power)
Blyth Harbour Wind Farm (re-power) is an operational 3.4 MW onshore wind farm in Northumberland, generating since 1 September 2012. Planning permission was granted on 21 July 2008, 13 months after submission. Operator of record: Hainsford Energy.
Planning and build timeline
| Application submitted | 6 July 2007 |
| Permission granted | 21 July 2008 13 months after submission |
| Operational | 1 September 2012 49 months after consent |
Screening a site of your own?
Northumberland approves 52% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Blyth Harbour Wind Farm (re-power)’s recorded coordinate — swap in your own postcode or coordinates.
Northumberland’s record on onshore wind
Northumberland has decided 31 onshore wind schemes and approved 52%, taking a median of 16.3 months. See every onshore wind scheme decision in Northumberland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 2.7 | 0.5 km |
Solar Photovoltaics · Operational | 2.3 | 2.6 km |
Landfill Gas · Operational | 4.1 | 7.8 km |
Wind Onshore · Operational | 4 | 8.3 km |
Wind Onshore · Operational | 26 | 8.5 km |
Biomass (dedicated) · Operational | 27.7 | 8.5 km |
Biomass (dedicated) · Operational | 420 | 8.9 km |
Wind Offshore · Operational | 41.5 | 9.6 km |
How big is Blyth Harbour Wind Farm (re-power)?
Blyth Harbour Wind Farm (re-power) has a recorded installed capacity of 3.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Blyth Harbour Wind Farm (re-power)?
REPD records the operator as Hainsford Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Blyth Harbour Wind Farm (re-power) approved and built?
The application was submitted on 6 July 2007. Permission was granted on 21 July 2008, 13 months later. The site became operational on 1 September 2012, 49 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4663.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode