Renewable sites › Goathill Quarry Turbine
Goathill Quarry Turbine
Goathill Quarry Turbine is an operational 2 MW onshore wind farm in Fife, generating since 27 December 2015. Planning permission was granted on 21 June 2013, 20 months after submission. Operator of record: Collier Quarrying Group.
Planning and build timeline
| Application submitted | 1 November 2011 |
| Permission granted | 21 June 2013 20 months after submission |
| Operational | 27 December 2015 30 months after consent |
Screening a site of your own?
Fife approves 54% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Goathill Quarry Turbine’s recorded coordinate — swap in your own postcode or coordinates.
Fife’s record on onshore wind
Fife has decided 28 onshore wind schemes and approved 54%, taking a median of 16.1 months. See every onshore wind scheme decision in Fife →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 4.6 | 0.5 km |
Battery · Operational | 49.99 | 4.2 km |
Solar Photovoltaics · Operational | 1.9 | 5.1 km |
Wind Onshore · Operational | 6.9 | 5.5 km |
Wind Onshore · Operational | 25 | 5.6 km |
Biomass (dedicated) · Operational | 12.5 | 6.2 km |
Wind Onshore · Operational | 10 | 6.7 km |
EfW Incineration · Under Construction | 23.7 | 7.9 km |
How big is Goathill Quarry Turbine?
Goathill Quarry Turbine has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Goathill Quarry Turbine?
REPD records the operator as Collier Quarrying Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Goathill Quarry Turbine approved and built?
The application was submitted on 1 November 2011. Permission was granted on 21 June 2013, 20 months later. The site became operational on 27 December 2015, 30 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4088.