Renewable sites › Kilmarnock South Substation - Battery storage
Kilmarnock South Substation - Battery storage
Kilmarnock South Substation - Battery storage is operational in Scotland with a recorded capacity of 300 MW, and has been generating since 2026-01-21.
Planning and build timeline
| Application submitted | 2022-02-22 |
| Permission granted | not recorded |
| Operational | 2026-01-21 |
Scottish Government (S36)’s record on battery storage
Scottish Government (S36) has decided 108 battery storage schemes and approved 94%, taking a median of 17.3 months. See every battery storage scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Elmbank Drive Solar Panels Solar Photovoltaics · Operational | — | 3.7 km |
Sneddon Law Community Wind Farm Wind Onshore · Under Construction | 45 | 8.6 km |
GlaxoSmithKline Wind Project (Turbine 4) Wind Onshore · Operational | 2.5 | 9.6 km |
Glaxosmithkline Shewalton Road Solar Photovoltaics · Under Construction | 19.9 | 10.3 km |
GlaxoSmithKline (Waste AD) Anaerobic Digestion · Operational | 1 | 10.4 km |
Shewalton Road Wind Onshore · Under Construction | 3 | 10.6 km |
GlaxoSmithKline Wind Project Wind Onshore · Operational | 7.5 | 10.7 km |
Caledonian Papermill Biomass (dedicated) · Operational | 26 | 10.9 km |
How big is Kilmarnock South Substation - Battery storage?
Kilmarnock South Substation - Battery storage has a recorded installed capacity of 300 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kilmarnock South Substation - Battery storage?
REPD records the operator as Zenobe Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kilmarnock South Substation - Battery storage approved and built?
The application was submitted on 2022-02-22. REPD does not record a grant date. The site became operational on 2026-01-21.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9696.