Caledonian Papermill is operational in North Ayrshire with a recorded capacity of 26 MW, and has been generating since 2009-06-04.

26 MW
Capacity
as recorded in REPD
Operational
Status
since 2009-06-04
Biomass (dedicated)
Technology
Caledonian Paper
North Ayrshire
Authority
Scotland

Planning and build timeline

Application submitted2006-05-05
Permission granted2006-07-11
2 months after submission
Operational2009-06-04
35 months after consent

Other built sites within 15 km

SiteMWDistance
Oldhall Industrial Estate
EfW Incineration · Under Construction
171.6 km
GlaxoSmithKline (Waste AD)
Anaerobic Digestion · Operational
11.8 km
Shewalton Road
Wind Onshore · Under Construction
31.8 km
Glaxosmithkline Shewalton Road
Solar Photovoltaics · Under Construction
19.92 km
GlaxoSmithKline Wind Project (Turbine 4)
Wind Onshore · Operational
2.52 km
GlaxoSmithKline Wind Project
Wind Onshore · Operational
7.52.1 km
Shewalton Landfill Solar Farm
Solar Photovoltaics · Under Construction
52.1 km
Nethermains - Solar Farm
Solar Photovoltaics · Under Construction
7.54.3 km

How big is Caledonian Papermill?

Caledonian Papermill has a recorded installed capacity of 26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Caledonian Papermill?

REPD records the operator as Caledonian Paper. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Caledonian Papermill approved and built?

The application was submitted on 2006-05-05. Permission was granted on 2006-07-11, 2 months later. The site became operational on 2009-06-04, 35 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 34.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council