Renewable sites › Elmbank Drive Solar Panels
Elmbank Drive Solar Panels
Elmbank Drive Solar Panels is operational in East Ayrshire, and has been generating since 2021-12-02.
Planning and build timeline
| Application submitted | 2021-01-28 |
| Permission granted | 2021-08-20 7 months after submission |
| Operational | 2021-12-02 3 months after consent |
East Ayrshire’s record on solar
East Ayrshire has decided 6 solar farms and approved 100%, taking a median of 2.6 months. See every solar farm decision in East Ayrshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Kilmarnock South Substation - Battery storage Battery · Operational | 300 | 3.7 km |
Sneddon Law Community Wind Farm Wind Onshore · Under Construction | 45 | 7.2 km |
GlaxoSmithKline Wind Project (Turbine 4) Wind Onshore · Operational | 2.5 | 8.2 km |
Glaxosmithkline Shewalton Road Solar Photovoltaics · Under Construction | 19.9 | 8.7 km |
GlaxoSmithKline (Waste AD) Anaerobic Digestion · Operational | 1 | 8.9 km |
GlaxoSmithKline Wind Project Wind Onshore · Operational | 7.5 | 9 km |
Shewalton Road Wind Onshore · Under Construction | 3 | 9.1 km |
Oldhall Industrial Estate EfW Incineration · Under Construction | 17 | 9.5 km |
How big is Elmbank Drive Solar Panels?
REPD does not record an installed capacity for Elmbank Drive Solar Panels.
Who operates Elmbank Drive Solar Panels?
REPD records the operator as Centrestage Communities Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Elmbank Drive Solar Panels approved and built?
The application was submitted on 2021-01-28. Permission was granted on 2021-08-20, 7 months later. The site became operational on 2021-12-02, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8432.